Buying a Property: Inspection Guides

Quick Answer:What are the building inspection stages in Victoria? For a new home, the building surveyor inspects at the mandatory stages listed on your building permit. These are typically before footings are placed, before any nominated reinforced concrete is poured, at frame completion and at final completion. Many homeowners also book five independent construction-stage inspections: pre-slab, frame, lock-up/pre-plaster, fixing, and practical completion. Each is timed to check work before concrete, plasterboard or tiles cover it.
Buying a Property

Key Takeaways

  • Mandatory building surveyor inspections and independent stage inspections are separate systems. An independent report does not replace statutory approval.
  • Contract payment stages, mandatory notification stages and independent inspection checkpoints often overlap but are not the same thing.
  • The most valuable inspections are the ones timed before work is hidden: pre-slab, frame and pre-plaster.
  • Wet-area waterproofing needs its own check before tiling. A finished shower can’t show the membrane underneath.
  • In Geelong, soil class, flood overlays, coastal exposure and bushfire status are set lot by lot, and they change what the work is checked against.
  • NCC 2025 (from 1 May 2026), First Resort Home Warranty (from 1 July 2026) and the 2026 Guide to Standards and Tolerances (from 1 August 2026) apply depending on your project and contract dates.

The frame is up. The roof trusses are on. Your builder has sent the frame-stage progress claim, and from the footpath the house looks exactly like the plans.

What you can’t see from the footpath is whether the bracing panels are nailed to the engineer’s schedule, whether the tie-downs are in the right places, or whether the lintel over the stacker door is the size the framing plan specified. In a few weeks, wall wrap, cladding and plasterboard will cover most of it.

That is the core idea behind building inspection stages in Victoria. Construction progress, payment milestones and inspection points are linked, but they are not the same thing. A stage can be finished, invoiced and approved by the building surveyor while workmanship issues remain that nobody has looked at yet.

This guide walks through the five construction stage inspections most homeowners book:

  1. Pre-slab
  2. Frame
  3. Lock-up / pre-plaster
  4. Fixing
  5. Practical completion/handover

 

It also covers additional hold points to consider, such as a wet-area waterproofing check before tiling. The principle throughout is simple: inspect critical work while it is still visible.

Each stage inspection is a visual check of the work that is visible and accessible on the day. The inspector compares it with the approved drawings, engineering details and specifications, flags defects before later trades cover them, and records the findings in a written report with photographs. Scope depends on access, the documents available and the service booked. A visual inspection cannot assess work that is already covered, test concealed materials or certify engineering design.

Table of Contents

Mandatory Building Surveyor Inspections vs Independent Construction Stage Inspections

There are two separate inspection systems on most Victorian new-home builds. They serve different people and have different legal weight.

Mandatory inspections are part of the building permit. Under the Building Act 1993 and Building Regulations 2018, the relevant building surveyor (RBS) decides which mandatory notification stages apply and lists them on the permit. 

For a new home, regulation 167 prescribes these stages: before placing a footing, before pouring an in situ reinforced concrete member nominated by the RBS, on completion of the frame, and on completion of all building work. The builder must notify the RBS when each stage is complete, and only the RBS can trigger the mandatory inspection. BPC Practice Note MI 01 sets out these roles.

The RBS can omit a prescribed stage that is not relevant to the work, and can require other inspections (for example, waterproofing or energy-efficiency features) as a permit condition. Check your building permit for the stages that apply to your project.

Independent inspections are commissioned by you, the owner. A private inspector assesses workmanship, visible defects and incomplete work, and reports to you. MI 01 notes that an owner may request an inspection for due diligence or quality control, but that such inspections sit outside the mandatory process. An independent report does not replace a statutory inspection and does not give regulatory approval.

Inspection type Who arranges it Main purpose Does it replace statutory approval?
Mandatory notification stage inspection Builder notifies the relevant building surveyor, who carries out or causes the inspection Assess compliance with the Building Act, Regulations and building permit up to that stage It is the statutory inspection
Additional inspection required by the RBS (permit condition) Builder, as directed by the permit Check specific elements the RBS nominates, such as waterproofing Forms part of the permit process
Independent construction stage inspection Homeowner Independent record of visible workmanship, defects and incomplete work No
Builder's own quality checks or engineer inspections Builder Internal quality control or engineering verification No, unless the RBS has authorised the person for a mandatory inspection

Payment Stages, Mandatory Stages and Inspection Checkpoints Are Three Different Systems

Homeowners often assume “frame stage” means the same thing to the builder, the building surveyor and the inspector. It rarely does. Your contract defines when a progress payment falls due. The building permit defines when the surveyor must be notified. An independent inspection is timed around what you want to see before it is covered.

Point in the build

Contract progress-payment stage

Mandatory notification stage (typical new home)

Useful independent checkpoint

Footings and slab

Base stage. For a concrete floor, generally when the floor is complete

Before placing a footing; before pouring any in situ reinforced concrete member the RBS nominates

Pre-slab, after reinforcement and membrane are in and before the pour

Structure

Frame stage. The frame is complete and approved by a building surveyor

Completion of frame

Frame, before wall wrap, insulation and linings hide structural details

Envelope

Lock-up stage. External cladding and roof covering fixed, flooring laid, external doors and windows installed

None prescribed (the RBS may add conditions)

Lock-up / pre-plaster, while insulation, sarking and services are still visible

Wet areas

Usually inside the fixing stage

None prescribed (the RBS may nominate waterproofing)

Membrane check after waterproofing, before tiling

Internal fit-out

Fixing stage. Internal linings, architraves, skirting, doors, cabinets and fixtures fitted

None prescribed

Fixing stage

Completion

Final payment, generally once the occupancy permit is issued and work matches the plans and specifications

Completion of all building work (occupancy permit or certificate of final inspection)

Practical completion / handover, before the final payment

Payment-stage descriptions are summarised from Consumer Affairs Victoria. Your own contract’s definitions and payment schedule apply, and domestic building contract laws have been amended recently, so read the schedule in the contract you signed.

Why it matters: reaching the lock-up payment stage tells you the house is closed in. It tells you nothing about whether the shower membrane has been installed correctly, because that work may not have started yet. A dedicated waterproofing inspection has to be timed to the waterproofing, not to the invoice.

The Five Inspection Stages of a New Home Build

Most independent stage inspections follow five visits, each timed to the last good look at a set of building elements. This section is the overview. For a detailed walkthrough of each visit, read The 5 Construction Stage Inspections, Explained.

Stage

Best time to inspect

Main elements assessed

What may become inaccessible afterwards

1. Pre-slab

Formwork, reinforcement, membrane and penetrations in place; before the concrete pour

Set-out, edge and internal beams, reinforcement and supports, vapour barrier, plumbing penetrations, termite management details

Reinforcement, membrane, under-slab services

2. Frame

Wall and roof frames complete; before wall wrap, insulation and linings

Bracing, tie-downs, connections, trusses, lintels, alignment

Structural fixings and connections

3. Lock-up / pre-plaster

Roof, cladding, windows and external doors on; insulation and services in; before plasterboard

Flashings, sarking, wall wrap, window installation, insulation, service penetrations

Insulation, wall wraps, internal flashings, in-wall services

4. Fixing

Linings, joinery, cabinetry and fixtures installed

Internal finishes, doors, joinery, cabinetry, wet-area finishes

Most remaining substrates once painting and fit-off finish

5. Practical completion

Builder says the work is complete; before handover and final payment

Visible defects, incomplete work, finishes, fixtures, accessible roof space and exterior

Your simplest chance to have the builder fix items before you move in

Stage 1 – Pre-Slab: Before the Concrete Is Poured

This visit occurs once the formwork, reinforcement, the vapour barrier, and plumbing penetrations are in place, and before the pour. The inspector compares set-out, beams, reinforcement and membrane with the engineer’s drawings, which are generally designed under AS 2870 and the NCC. Once the concrete is in place, checking the reinforcement means coring the slab.

Before you book: ask for the soil report and approved footing design. Your contract’s base-stage payment may fall due after the pour, not at this inspection.

Stage 2 – Frame: Before the Structure Is Concealed

This visit happens when wall frames and roof trusses are complete, before wall wrap, insulation and linings. The focus is bracing, tie-downs, connections, trusses and lintels, checked against the framing documentation. Timber frames commonly follow the AS 1684 series; steel frames follow their own design and manufacturer specifications. A strap tie-down that takes seconds to check now means cutting plasterboard later.

Before you book: confirm the building surveyor’s frame inspection has been completed.

Stage 3 – Lock-Up / Pre-Plaster: Before the Walls Are Lined

Lock-up is a payment stage. Pre-plaster is the last moment insulation and in-wall services are visible. This visit looks at flashings, window installation, wall wraps, sarking, insulation and ventilation. New homes must meet a 7-star NatHERS rating and a Whole of Home budget, and NCC 2025 strengthens condensation management for external walls and roof ventilation.

Before you book: confirm insulation and wraps will still be visible on the day. Some builders plaster within days of insulating.

Stage 4 – Fixing: Internal Workmanship and Wet Areas

This visit happens once linings, joinery, cabinetry and fixtures are installed. It covers finishes, doors and joinery, and whether what was installed matches the contract specifications.

A finished tiled shower hides its membrane. If you want waterproofing checked, book a separate visit after the membrane cures and before tiling. The NCC Housing Provisions set the requirements, and AS 3740 is one recognised compliance pathway.

Stage 5 – Practical Completion: Before Handover

This visit happens when the builder says the home is complete, before you accept handover and make the final payment. It records visible defects and incomplete work, assessed against the NCC, your contract and the Guide to Standards and Tolerances. The 2026 edition applies to contracts entered into or work started from 1 August 2026.

The practical completion inspection, the contractual handover and the building surveyor’s occupancy permit are three different things. Practical Completion and Handover: What to Expect explains how they fit together. Ripple’s practical completion inspection covers the visit itself.

The Last Opportunity to Inspect Concealed Work

Every build has a short window for each hidden element. Miss it, and later assessment usually means specialist investigation or opening up finished work.

Construction element

When to inspect

What may conceal it later

Why inspection timing matters

Slab reinforcement and bar chairs

After steel is fixed, before the pour

Concrete

Cover and placement can only be checked by coring or scanning once poured

Under-slab vapour barrier and penetrations

Before the pour

Concrete

Tears and unsealed penetrations are invisible afterwards

Wall bracing and tie-downs

Frame complete, before wraps and linings

Wall wrap, insulation, plasterboard, cladding

Checking fixings later means removing linings

Window flashings and wall wraps

After windows and wraps are fitted, before cladding or plaster closes them in

Cladding, render, architraves

Water entry often shows up long after the cause is covered

Wall and ceiling insulation

After installation, before plasterboard

Plasterboard

Gaps and compression reduce performance and can add condensation risk

Wet-area membranes

After waterproofing cures, before tiling

Screed and tiles

Membrane failures are found by leaks, often months later

A visual inspection can only report what is visible on the day. It cannot establish the condition of every concealed element, and some issues will need testing or specialist assessment.

Which Additional Inspections Are Worth Considering During Construction?

The five standard stages cover most builds. Some projects benefit from extra hold points, depending on the design, site conditions, and any concerns that arise during construction.

  • Post-slab check where there is a specific concern, such as visible cracking, edge damage or questions about slab levels.
  • Wet-area waterproofing before tiling, for the reasons covered under Stage 4.
  • Insulation and condensation-control check if the builder plans to plaster soon after insulation goes in, so the lock-up visit would miss it.
  • Re-inspection of significant defects to confirm rectification before the work is covered or before the next payment.
  • Post-handover defect assessment if problems emerge after you move in. Ripple’s builder’s warranty inspections cover this stage.

 

These are project-specific checkpoints, not part of a standard five-stage package. Confirm availability and scope with your inspector before relying on them.

Which Building Codes and Australian Standards Apply to New Homes in Victoria?

A new Victorian home has to satisfy several layers of requirements at once. A simplified way to picture them, from the top down:

  1. Building Act 1993 – the primary legislation for building work, permits and practitioners.
  2. Building Regulations 2018 – detailed rules, including mandatory notification stages and NCC adoption.
  3. National Construction Code and Victorian variations – the technical performance requirements for the building.
  4. Referenced Australian Standards and other compliance pathways – the documents the NCC calls up to show compliance.
  5. Approved permit documents – the endorsed drawings, engineering and specifications for your project.
  6. Your building contract – workmanship, materials and quality obligations agreed with the builder.

This is a simplification. Exactly which obligations apply to your home depends on the permit, the NCC edition, the approved design and the contract. The Victorian Government’s building standards page is a useful starting point.

 

NCC 2025 and Its Application to New Homes

Victoria adopted NCC 2025 on 1 May 2026. Under a section 10(2) exemption in the Building Act, the relevant building surveyor can allow a project to proceed under NCC 2022 if substantial progress had been made on its design before that date, and some provisions have a one-year transition (BPC). Your building surveyor should confirm which edition applies to your project.

For housing, NCC 2025 is a smaller step than NCC 2022 was. The relevant areas for an inspector include:

  • Structural safety – including updated referenced standards, such as wind loading
  • Water and weatherproofing – external walls, roofs and wet areas
  • Condensation management – strengthened requirements for external wall construction and roof ventilation
  • Energy efficiency – the 7-star and Whole of Home requirements introduced under NCC 2022 remain
  • Livable housing – where applicable to the dwelling under Victorian adoption

See the ABCB’s NCC site for the code itself.

 

Australian Standards Relevant to Each Inspection Stage

Standard

Relevant subject

Stage where it is most relevant

AS 2870

Residential slabs and footings

Pre-slab

AS 1684 series

Residential timber-framed construction

Frame

AS 3660.1

Termite management for new building work

Pre-slab, frame, completion

AS/NZS 3500 series

Plumbing and drainage

Pre-slab, fixing

AS 4773 series

Masonry in small buildings, where applicable

Frame to lock-up

AS 3959

Construction in bushfire-prone areas

Lock-up, completion

AS 3740

Domestic wet-area waterproofing (one compliance pathway)

Waterproofing, fixing

The edition that applies is the one referenced by the NCC edition governing your project. Not every standard applies to every house. A non-bushfire lot will not need AS 3959, and a steel-framed home is not built to AS 1684.

One common confusion: AS 4349.1 is the standard for pre-purchase inspections of existing buildings. It does not set the technical requirements that a new home must meet.

 

The 2026 Regulatory Changes and What They Mean for You

Change

Date

What it means for a homeowner

Why your project date matters

NCC 2025 adopted in Victoria

1 May 2026

Updated technical requirements, including condensation management

Designs substantially progressed before this date may proceed under NCC 2022

First Resort Home Warranty replaces domestic building insurance

1 July 2026

Homeowners can claim for defective, non-compliant or incomplete work without first exhausting other avenues

Contracts signed before this date stay under the old domestic building insurance scheme

Guide to Standards and Tolerances 2026

1 August 2026

Revised workmanship benchmarks used in discussions and disputes

Applies only to contracts entered into or work started from this date

7-star energy standard

In force since 1 May 2024

Insulation, glazing and sealing matter more at the pre-plaster stage

Continues under NCC 2025

What Geelong Homeowners Should Check Before Building Begins

Greater Geelong covers growth corridors, established suburbs, coastal towns and bushland edges. The site risks that shape a home’s design differ from lot to lot, and they decide which inspection details matter most.

Soil Reactivity and Foundation Design

Every new home starts with a site-specific soil test. It classifies how much the soil is likely to shrink or swell as moisture changes, from Class A (sand and rock) through S, M, H1, H2 and E, to Class P for problem sites. An endorsed engineer designs the footings to suit that classification (BPC).

The design only works if the site’s moisture conditions stay reasonably stable. Poor drainage, leaking pipes, garden beds against the slab and trees planted too close can all change soil moisture and move footings. BPC advises telling your builder about trees you plan to keep or plant before you sign the contract, so the engineer can allow for them.

Scenario A (hypothetical): A couple buys a house-and-land package in a new Armstrong Creek estate. Before the pre-slab inspection, they get the soil report and the engineer’s slab drawings from their builder. The inspector uses the drawings to check the beam layout and reinforcement shown for that lot. Months later, they use the same report to plan landscaping that keeps water away from the slab edge.

Flood-Prone Land, Drainage and Stormwater

Some Greater Geelong land is affected by stormwater flooding and covered by a Special Building Overlay (SBO). The City of Greater Geelong assesses building plans on this land to keep flood paths open and avoid worsening flooding. A planning permit is generally required for buildings and works in an SBO (City of Greater Geelong). The Corangamite Catchment Management Authority is responsible for riverine and coastal flood overlays.

If your land is affected, review:

  • Planning and building permit documents, including any flood-related conditions
  • Approved site levels and finished floor levels
  • The stormwater and drainage design
  • Any council or catchment authority approvals or flood advice

Scenario B (hypothetical): A lot in an established suburb sits partly within an SBO. The approved plans set a minimum finished floor level above the designated flood level. At the pre-slab stage, the homeowner asks the inspector to note the set-out and visible formwork heights, and asks the builder for the surveyor’s level confirmation. Only a licensed surveyor can confirm levels precisely.

Coastal Exposure and Building Materials

Homes in coastal areas such as Ocean Grove and other parts of the Bellarine Peninsula can face salt-laden air, stronger wind and driving rain. Relevant considerations include:

  • Corrosion exposure for steel fixings, brackets, lintels and roofing
  • Fixings and materials rated for the site’s design exposure
  • Window and cladding weatherproofing details
  • The wind classification used for structural design
  • Ongoing maintenance, such as washing down exposed metalwork

Distance from the beach alone does not set the exposure classification. It comes from the design, site conditions and applicable standards.

Scenario C (hypothetical): A new home on the Bellarine is designed for a higher corrosion exposure than an inland lot. At the frame stage, the inspector compares visible connectors and fixings with the specification. At lock-up, they look closely at the window flashings and the roofing fixings as called for in the drawings.

Bushfire and Termite Requirements

If your lot is in a designated bushfire-prone area, a Bushfire Attack Level (BAL) assessment sets the minimum construction requirements under AS 3959. A lot assessed as BAL-Low must still be built to BAL-12.5 (City of Greater Geelong). Some properties are also covered by a planning overlay with further requirements.

Termite management for new work is addressed through the NCC and, where used, AS 3660.1. Whether a lot is in a designated termite area is a property-level question.

Councils can confirm these details through a property information certificate under regulation 51(2) of the Building Regulations 2018. It states whether land is in an area liable to flooding, designated as a termite area, subject to a specified BAL, or designated for snowfall (example council form). Requirements are set lot by lot, so do not assume your suburb’s status applies to your block.

Homeowner Document Checklist for Construction Inspections

An inspector can only compare the work with documents they can see. Gather these early and share the relevant ones before each visit.

Document

Where to get it

Most useful at

Building permit and endorsed drawings

Builder or building surveyor

Every stage

Engineering plans (slab, framing, bracing, tie-downs)

Builder

Pre-slab and frame

Soil report and site classification

Builder; usually with permit documents

Pre-slab

Contract specifications and signed variations

Your contract file

Fixing and practical completion

BAL assessment, where applicable

Builder or BAL assessor

Lock-up and completion

Energy rating documentation (NatHERS certificate, stamped plans)

Builder or energy assessor

Lock-up / pre-plaster

Truss and frame layouts

Builder or frame supplier

Frame

Termite management details

Builder

Pre-slab and completion

Records of mandatory surveyor inspections

Builder or surveyor; owners can request approved inspection dates from council under regulation 51(3)

Before each progress payment

  • Request permit documents and engineering plans before the slab is poured
  • Confirm the BAL and any flood or overlay requirements for your lot
  • Keep every signed variation with the contract
  • Ask the builder to confirm each mandatory inspection has passed before paying

When Should You Book an Independent Building Inspector?

Book your inspector before construction starts, then confirm each visit as the build approaches that stage. The hard part is not the booking. It is getting enough notice from the site.

A practical sequence:

  1. Before signing or at contract stage: check what your contract says about owner access and independent inspections. Raise it with the builder in writing early.
  2. Before site start: give the builder your inspector’s details and ask the site supervisor to notify you ahead of each key milestone.
  3. Before each stage: confirm access, any site induction or safety requirements, and written permission if the builder requires it.
  4. Before work is covered: ask specifically for notice before the slab pour, before wall wraps and insulation are covered, and before tiling.
  5. After each report: allow time to send findings to the builder and get a response before the next stage closes the work in.

 

Build schedules move. Weather, deliveries and trades can bring a stage forward by days. Ask for as much notice as the builder can reasonably give, and confirm the day before.

What Should You Do if an Inspection Identifies Building Defects?

Put the findings in writing to your builder, with photos and references to the drawings or specifications, and ask for their proposed fix and timeframe. Get specialist advice for engineering, plumbing or electrical questions outside the inspector’s scope, and keep evidence of every rectification.

A private inspection report records an inspector’s observations. It is useful evidence, but it is not a legal finding that work is non-compliant. Consumer Affairs Victoria advises against withholding a progress payment due to defects once a stage is complete and recommends seeking legal advice before withholding any payment (CAV).

If you can’t resolve it with the builder, the Building and Plumbing Commission is Victoria’s building regulator and handles domestic building disputes. Building Defects and Disputes in Victoria walks through each option.

What Happens After Handover?

Keep all stage reports, the practical completion report, the occupancy permit, and all builder correspondence together. Write to the builder about any new or developing defects, with dates and photos.

Warranties and insurance are separate from stage inspections. From 1 July 2026, Victoria’s First Resort Home Warranty scheme, run by the Building and Plumbing Commission, replaced domestic building insurance for new eligible contracts over $20,000. Homeowners can claim for defective, non-compliant or incomplete work without first exhausting other options (Victorian Government;Consumer Affairs Victoria). Contracts signed before that date stay under the earlier scheme. Cover has eligibility rules, limits and exclusions, so not every defect will be covered.

Builder’s Warranty in Victoria explains both schemes and their time limits. If a warranty period is ending, Ripple’s builder’s warranty inspections document any visible defects that you can still raise.

How Ripple Building Inspections Supports New Home Builds in Geelong

Ripple Building Inspections provides independent construction-stage inspections across Greater Geelong, the Surf Coast, the Bellarine Peninsula, Golden Plains, and Melbourne’s northern, western, and south-eastern suburbs.

Our new home service covers the five stages in this guide: pre-slab, frame, lock-up (pre-plaster), fixing, and practical completion/handover. We have no ties to builders, agents or developers, so the report is written for you.

Each inspection is carried out by a qualified, experienced inspector. You get a phone summary after the visit and a digital report with photographs, advertised as delivered within 24 hours. Findings are sorted by severity, so you can see which items to raise first.

An independent report gives you something specific to discuss with your builder: the location, a photo and the reason it matters. It does not replace the building surveyor’s inspections or guarantee a defect-free home. It gives you a clear, dated record while the work can still be checked. 

new home inspection

The Practical Takeaway

Time your inspections to what is about to be covered, not to the invoice. Gather your documents early, ask for notice before each pour, wrap and tile, and put every finding to your builder in writing.

If you’re building in Geelong or Melbourne’s suburbs and want an independent set of eyes at each stage, talk to us about our Construction stage inspections in Geelong.

Building a New Home? Get Independent Eyes on Every Stage

Identify visible defects and workmanship issues before they are concealed or become more costly to address.

Frequently Asked Questions

For a new home, regulation 167 of the Building Regulations 2018 prescribes notification before placing a footing, before pouring any in situ reinforced concrete member the surveyor nominates, at frame completion, and at final completion. The relevant building surveyor lists the stages that apply on your permit and can add other required inspections as conditions. Independent stage inspections are optional.
It’s not a legal requirement. The surveyor checks compliance with the Act, Regulations and permit at set points. An independent inspector works for you, looks at visible workmanship and incomplete work, and gives you a written record. Many owners use both for that reason, especially on volume builds where stages move quickly.
Once formwork, reinforcement, the vapour barrier and plumbing penetrations are in place, and before the concrete pour. That window can be short, sometimes a day or two. Ask the builder to tell you when steel fixing is booked so your inspector can attend before the pour is scheduled.
Yes. A frame inspection is designed for exactly that point, as long as wall wraps, insulation and linings are not yet covering the structural details. If cladding or plasterboard has already gone on in parts of the house, the inspector can only report on what is still visible.
Usually, yes, if timing allows. Consumer Affairs Victoria advises checking that each stage is complete, has passed any required surveyor inspection and meets the contract before paying. A stage report can help with that check. Don’t withhold payment without reading your contract and getting legal advice.
Most owners book the five standard stages. Add a waterproofing inspection if you want the membranes checked before tiling, and a re-inspection if significant defects need verifying. A smaller budget is often best spent on the stages that hide the most: pre-slab, frame and pre-plaster.
The inspector can only report on what is visible. They may note the limitation and look for indirect signs, such as cracking or misalignment. Opening up covered work is a matter between you, the builder and possibly the building surveyor. Agree notice periods in writing early so this doesn’t happen again.
The state rules are the same. What differs is the site: soil classification, flood overlays, coastal exposure, bushfire designation and termite areas vary across Greater Geelong. These change the approved design, and therefore what an inspector checks the work against.

Owner-builders follow the same mandatory inspection process through their building surveyor. If you plan to sell within six and a half years of completion, Victorian law requires a defects report from a prescribed building practitioner. Ripple prepares owner-builder reports for this purpose and offers general building inspections for other needs.