The 5 Construction Stage Inspections, Explained
Quick answer: Construction-stage inspections are independent checks of a new home at five points: pre-slab, frame, lock-up/pre-plaster, fixing, and practical completion. Each is timed just before concrete, cladding, plaster, tiles or occupancy hide the work. They add an owner-focused review to the building surveyor’s mandatory inspections, but do not replace them or guarantee a defect-free home.
Key Takeaways
- Each inspection is timed just before the next trade conceals the work, when defects are easiest to see and cheapest to fix.
- Independent inspections complement the building surveyor’s mandatory inspections; they do not replace them.
- Pre-slab and pre-plaster cover the most concealed work, so their booking windows are the easiest to miss.
- Requirements depend on your property and approved documents, including whether your permit falls under NCC 2025 or NCC 2022.
- Geelong sites can carry bushfire, flood, coastal, soil, or termite requirements that change which stages are checked.
- Raise findings in writing, keep a log, and get advice before withholding any progress payment.
Most of a new house disappears as it is built. Concrete covers the reinforcement and termite measures. Cladding and plaster cover the frame, tie-downs, insulation and services. Tiles cover the waterproofing. Once an element is hidden, checking it usually means waiting for a symptom or opening up finished work.
Construction stage inspections are built around that problem. Each one is timed to look at work while it can still be seen, measured and photographed, and while fixing it is still relatively simple.
This guide explains the five independent inspection stages Ripple Building Inspections offers on new homes in Geelong and Melbourne: what each stage covers, what the next trade will conceal, which requirements may apply, and how to book and act on the findings.
Table of Contents
Independent Inspections vs Mandatory Building Inspections
Victoria already has inspections built into the permit system, so it is fair to ask what an independent inspection adds. The two serve different clients and purposes.
Mandatory (statutory) inspections. You, not your builder, must appoint the relevant building surveyor, who issues the permit and carries out mandatory inspections at key stages (BPC).
For a new building, regulation 167 of the Building Regulations 2018 prescribes the stages, and the surveyor lists the applicable ones on your building permit (BPC Practice Note MI-01).
For a house, these are typically: before placing a footing, before pouring an in-situ reinforced concrete member the surveyor nominates, completion of framework, and completion of all building work (ABLIS).
The builder must notify the surveyor at each stage and must not cover work until it has been inspected and approved (BPC MI-01).
The surveyor may also require additional inspections as a permit condition, for example, waterproofing or energy-efficiency features, but these are not mandatory notification stages (BPC MI-01). If work is non-compliant, the surveyor can direct the builder to fix it (BPC).
Independent inspections. An independent inspector is engaged by you. The Building and Plumbing Commission notes you may choose an independent inspector to check key stages before progress payments (BPC). Consumer Affairs Victoria says the same (CAV). An independent report can cover workmanship and contract matters as well as compliance, and it is written for you.
| Inspection criteria | Mandatory inspection | Independent inspection |
|---|---|---|
| Engaged by | Relevant building surveyor (appointed by the owner) | The owner |
| Required by law | Yes, at prescribed stages | No |
| Main focus | Compliance with permit, Act and regulations | Compliance, workmanship and contract, from the owner’s side |
| Report goes to | Building surveyor’s records | The owner, to share with the builder |
| Can issue directions | Yes (surveyor) | No; findings are raised through the builder and surveyor |
Independent inspections do not replace the surveyor’s inspections, and no inspection guarantees a defect-free home. They add a second, owner-focused set of eyes at the points where concealment happens.
The Five Stages at a Glance
| Stage | Typical timing | Key elements checked | What gets concealed next |
|---|---|---|---|
| 1. Pre-slab | Formwork, membrane, reinforcement and under-slab services in place; before the pour | Set-out, footing/beam set-up, reinforcement, vapour barrier, termite measures, penetrations | Everything below and inside the slab |
| 2. Frame | Wall and roof frames erected; before cladding and wall wrap close it in | Frame against drawings and engineering, bracing, tie-downs, lintels, trusses | Structure behind cladding, then plaster |
| 3. Lock-up / pre-plaster | External cladding, windows and roof on; insulation and rough-in done; before plasterboard | Wall wrap and flashings, insulation, services rough-in, wet-area preparation | Insulation, services and framing behind plasterboard |
| 4. Fixing | Plaster, internal doors, cabinetry, wet-area waterproofing and tiling under way | Linings, joinery, waterproofing (where visible), tiling, fixtures | Membranes under tiles; substrates under finishes |
| 5. Practical completion | Builder states the work is complete; before final payment and handover | Finishes, operation of fittings, external works, drainage, incomplete items | Leverage before final payment, and defects masked by occupancy |
The five stages broadly align with the base, frame, lock-up and fixing payment stages defined for Victorian domestic building contracts, with completion at the end (CAV). This is useful because payment milestones are a natural point to review the work. The contract defines when a stage is complete; check yours for the exact wording.
Stage 1: Pre-Slab Inspection — Checking the Foundations Before Concrete Is Poured
When to inspect: after the formwork, edge beams, reinforcement, under-slab membrane, termite management measures and under-slab plumbing are in place, and before the concrete pump arrives. The window can be a day or less, so book it early and ask your builder for the pour date as soon as it is set.
What is checked
- Set-out: slab position and dimensions against the site plan and setbacks.
- Footing and beam set-up: edge and internal beam sizes, depths and locations against the engineer’s slab design.
- Reinforcement: mesh and bar type, laps, bar chairs and cover to the reinforcement as specified.
- Vapour barrier or damp-proofing membrane: coverage, laps, taping and damage around penetrations.
- Termite management: whether the specified system (for example a physical collar at penetrations or a perimeter system) appears installed as documented.
- Penetrations and services: pipe locations, lagging, and whether pipes pass through beams where the design allows.
- Site drainage and excavation: water ponding in trenches, loose spoil and disturbance of the founding material.
Why these elements matter
Residential slabs and footings are designed and classified under AS 2870-2011, which NCC 2025 continues to reference (ABCB, NCC 2025 referenced documents). Sites are grouped by how much the soil is expected to move with moisture change: slightly (S), moderately (M), highly (H) and extremely (E) reactive clays, plus class P for problem sites such as soft soils, uncontrolled fill or abnormal moisture conditions (ABCB). Your engineer sizes beams and reinforcement for your site’s class. If the slab on site does not match that design, the footing system may not perform as intended.
What gets concealed
Everything. After the pour, you can no longer check reinforcement, beam depth, membrane laps or termite collars at slab penetrations. Fixing a problem found later typically involves engineering assessment, investigation or rectification work rather than a simple adjustment.
Relevant requirements
- Regulation 167 mandatory notification stages before placing a footing and, where the surveyor nominates it, before pouring an in-situ reinforced concrete member (BPC MI-01). The BPC notes a pre-slab inspection also covers siting, not just footings and beams.
- NCC footing and slab provisions and AS 2870-2011.
- AS 3660.1 for termite management where it is required for the site (see Termites below).
- Any minimum floor level set through a council report and consent on land liable to flooding (see Flooding below).
- The approved engineering drawings and site classification report.
Hypothetical example: An engineering drawing calls for an internal stiffening beam under a load-bearing wall. On site, the trench has been dug but partly backfilled after rain. Photographing and reporting it before the pour lets the builder and engineer resolve it in hours; after the pour, establishing what was built requires core drilling or excavation.
Stage 2: Frame Stage Inspection — Reviewing the Structural Framework
When to inspect: once wall frames, roof trusses or rafters, and structural members such as beams and lintels are installed and braced, and before wall wrap and cladding close the frame in. Ideally book it close to the building surveyor’s frame inspection, so any items both of you raise can be resolved together. Consumer Affairs Victoria describes the frame stage as complete when the frame is finished and approved by a building surveyor (CAV).
What is checked
- Frame against the drawings: wall locations, openings, ceiling heights and roof shape.
- Member sizes and grades: studs, plates, lintels and beams against the engineering or framing documentation.
- Bracing: bracing walls and sheet or strap bracing in the locations and quantities documented, with the specified fixings.
- Tie-downs and connections: straps, brackets, bolts and nailing patterns that hold the roof to the walls and the walls to the slab.
- Roof trusses: truss layout against the manufacturer’s layout, temporary and permanent bracing, girder-truss support, and point loads carried down to the slab.
- Straightness and plumb: visible bowing, twisting or out-of-plumb walls that will show through linings. Acceptable tolerances are defined by applicable standards and guides, so the report records observations rather than inventing limits.
- Damage and modification: notched or drilled members, cut truss chords and trimmed studs around services.
Why these elements matter
The frame is the load path. Wind uplift on the roof has to pass through trusses, tie-downs and wall framing into the slab. Racking forces are resisted by bracing walls. A missing strap or an unauthorised cut in a truss chord may not show until the house is under load, and by then it is behind plaster.
Timber-framed houses are commonly designed under AS 1684. NCC 2025 references Amendment 1 of the 2021 edition of AS 1684.2 (non-cyclonic areas) and the 2024 edition of AS 1684.4 (simplified) (ABCB, NCC 2025 list of amendments). Nailplated timber trusses are installed and braced to AS 4440 and the truss manufacturer’s layout and bracing specification (HIA). Steel frames follow their own referenced standards and manufacturer requirements.
Wind classification under AS 4055 drives tie-down and bracing requirements; NCC 2025 references Amendment 1 of its 2021 edition (ABCB). Exposed coastal and hilltop sites around Geelong can carry higher wind classifications than sheltered suburban lots, so check the classification shown on your approved documents.
What gets concealed
Wall wrap and cladding conceal the outside face of the frame. Plasterboard later conceals the inside. Roof framing stays technically accessible through the ceiling space, but insulation and limited access make thorough checks harder after lock-up.
Relevant requirements
- Completion of framework is a regulation 167 mandatory notification stage (BPC MI-01).
- NCC structural provisions; AS 1684 and AS 4055 as referenced by the applicable NCC edition; AS 4440 and the truss manufacturer’s documentation.
- Approved engineering, bracing and tie-down plans.
Hypothetical example: A plumber cuts through the bottom chord of a truss to run a stack vent. It is a small cut and easy to miss once the ceiling is up. At frame stage, it can be photographed and referred to the truss manufacturer or engineer for a repair detail.
Stage 3: Lock-Up and Pre-Plaster Inspection — Before the Walls Are Covered
When to inspect: when the roof covering, external cladding, windows, and external doors are installed, and the electrical, plumbing, and mechanical rough-ins and wall insulation are in, but before plasterboard goes up. Lock-up is a contractual payment stage, while “pre-plaster” refers to the physical condition to be inspected. On many projects, they are a few days apart, so confirm the plasterboard delivery date with your builder.
What is checked
- Weatherproofing of the envelope: wall wrap continuity, laps and taping; flashings at window heads, sills and jambs; and penetrations through the wrap.
- Windows and external doors: installation, packing, flashing and visible damage.
- Roof covering: sarking, flashings, valleys and gutters where visible and safely accessible.
- Insulation: wall insulation type, coverage and gaps, compared with the approved energy rating documentation and stamped specification.
- Services rough-in: pipe and cable routes, clipping and protection where they pass through framing, and penetrations through top plates.
- Wet-area preparation: framing and noggings for fixtures, and substrate preparation ahead of waterproofing.
- Frame items carried over: whether items raised at frame stage appear to have been addressed.
Why these elements matter
Moisture and energy performance are decided largely at this stage. NCC 2025 strengthened minimum condensation management requirements, including changes to external wall construction and roof ventilation to reduce moisture risk (HIA). Whether your project is assessed under NCC 2025 or NCC 2022 depends on its permit and transitional status (see below), so the inspector checks against the documents approved for your build.
Insulation is a common gap between the energy rating and the finished house. The rating assumes specific insulation in specific places; gaps, compression or missing batts behind a shower wall reduce that performance and become hard to detect once plaster is fixed.
Victoria also introduced lead-free requirements for plumbing products in contact with drinking water: from 1 May 2026, plumbing installations commencing on or after that date must use lead-free products, regardless of when the permit or contract was issued (BPC). Product compliance is the licensed plumber’s responsibility and is covered by their compliance certificate; a building inspection records visible rough-in issues rather than certifying plumbing products.
What gets concealed
Plasterboard hides the inside face of the frame, insulation, wall wrap from inside, cable and pipe routes, and fixing points for cabinetry and grab rails. This is often the last practical point to see the inside of the walls.
Relevant requirements
- NCC Volume Two / Housing Provisions weatherproofing, condensation management and energy efficiency provisions for the applicable edition.
- The approved energy rating documentation and stamped plans.
- Manufacturer installation instructions for wall wraps, windows and cladding, which the NCC 2025 condensation provisions make particularly relevant (HIA).
- Plumbing Regulations 2018 and the plumber’s compliance certificate for plumbing work.
Hypothetical example: Wall wrap has been cut back around a window opening and not re-lapped over the head flashing. From outside, the cladding looks fine. Before plastering, the gap is visible from the inside and can be repaired by removing a few cladding boards. After plaster and paint, the first sign may be staining below the window.
Stage 4: Fixing Stage Inspection — Checking Interior Work Before Final Finishes
When to inspect: after plasterboard is fixed and set, internal doors, architraves, skirtings and cabinetry are installed, and wet areas are waterproofed and tiled or being tiled. If you want the waterproofing membrane itself inspected, ask your builder when it will be applied and arrange a visit before the tiler starts. Once tiles are laid, a visual inspection can only assess the surface and indirect signs.
What is checked
- Wall and ceiling linings: fixing, jointing, cracking and visible defects in plasterboard before painting finishes it.
- Internal joinery: doors, frames, architraves, skirtings and cabinetry installation, alignment and damage.
- Wet areas: membrane coverage and upturns where the membrane is visible; falls in shower floors; junctions at hobs, screens, floor wastes and penetrations; and tiling workmanship.
- Fixtures: installation of vanities, basins, tapware and accessories where already fitted.
- Stairs and balustrades: installation and visible fixings, where present.
Why these elements matter
Water leaks from showers and bathrooms are among the more disruptive defects to fix after handover, because the repair usually means removing tiles. NCC 2025 references AS 3740-2021, Waterproofing of domestic wet areas (ABCB, NCC 2025 referenced documents), and the same edition was referenced under NCC 2022. The BPC lists waterproofing as an example of work a building surveyor may require an additional inspection for (BPC MI-01), so check your permit conditions too.
The fixing stage is also when most visible finish defects first appear. Recording them now, before painting and final cleaning, makes it clearer what existed before and what may arise later.
What gets concealed
Tiles conceal membranes, bond breakers and substrate falls. Paint conceals plaster jointing defects until light catches them. Cabinetry conceals wall linings and some services.
Relevant requirements
- NCC wet-area provisions and AS 3740-2021.
- Any additional waterproofing inspection set as a permit condition.
- Waterproofing installer’s documentation and any certification the builder obtains.
- The contract specification for finishes, fittings and inclusions.
Hypothetical example: A shower floor has been tiled with a visible fall away from the waste in one corner. Raised at fixing stage, the tiler can address it before the screen is installed. Raised after handover, the fix typically involves lifting tiles and potentially the membrane.
Stage 5: Practical Completion Inspection — The Final Check Before Handover
When to inspect: after the builder notifies you that the work is complete and before you make the final payment and accept the keys. Book it as soon as you receive the completion notice, and follow the completion steps and timeframes set out in your contract.
What is checked
- Interior finishes: paint, plaster, flooring, tiling, joinery and benchtops, inspected for defects and damage.
- Operation: doors, windows, locks, drawers, tapware and visible fittings opening, closing and draining as they should.
- Wet areas: visible sealants, grout, screens, falls and drainage.
- Exterior: cladding, brickwork, roof and gutters where safely visible, eaves, external doors, paths and the finished ground around the house.
- Site drainage and ground levels: whether finished ground and paving fall away from the house and stormwater appears connected.
- Incomplete work: items in the contract or plans that have not been delivered.
- Earlier items: whether defects raised at previous stages appear resolved.
Why these elements matter
Completion is the point where your leverage and the builder’s attention are both highest. Before final payment, outstanding items are part of the finishing process. After handover, they become warranty or defect claims, which tend to take longer.
The building surveyor also carries out a final inspection and, for a new house, issues an occupancy permit; the BPC notes that it is illegal to move in without one (BPC). An occupancy permit confirms that the building is suitable for occupancy. It is not a quality certificate for finishes or a statement that the house is free of defects.
The external ground matters more than many owners expect. Reactive clay sites move with moisture change (ABCB), so drainage that falls away from the house helps keep moisture conditions around the footings stable. Ponding against the slab edge, or a garden bed built over a termite barrier, can undo good work below ground.
What gets concealed
At this stage, the issue is less about physical concealment and more about what occupancy masks. Furniture, curtains and stored items cover walls and floors. Normal wear makes it harder to show which marks were there at handover.
Relevant requirements
- Mandatory notification on completion of all building work (ABLIS) and the occupancy permit or certificate of final inspection, as specified on the building permit.
- Your major domestic building contract: scope, specification and completion provisions.
- Domestic Building Contracts Act 1995, which governs domestic building contracts in Victoria (CAV).
Hypothetical example: Landscaping has raised garden soil above the slab edge along one side of the house. Inside, everything looks finished. Raising it before handover lets the levels be corrected while the landscaper is still engaged.
What Makes Construction Stage Inspections Important for Geelong Homes?
Greater Geelong covers inland growth corridors, established suburbs, the Bellarine coast and bushland edges. That range means two new homes a few kilometres apart can have quite different design requirements. The requirements for your home come from your property and your approved documents, not from the suburb name. The points below explain what to look for in those documents.
Which code edition applies to your build?
Victoria adopted NCC 2025 on 1 May 2026 (BPC). It does not automatically apply to every house under construction. The BPC explains that, under a section 10(2) exemption in the Building Act 1993, the relevant building surveyor can allow construction under NCC 2022 where substantial progress was made on the design before 1 May 2026, and that some provisions also carry a one-year transition (BPC). Ask your building surveyor which edition your permit is assessed under. A good inspector will check against that edition and your approved documents.
Soil and footings
Greater Geelong’s soils range from sandy loams to basalt plains; the volcanic plains extend north of the city towards the You Yangs (Wikipedia, Geelong geography). Residual basaltic clays in Victoria are known to be highly reactive, and basaltic clay sites are generally classified as Class H or Class E under AS 2870 (Engineering design and earthworks aspects related to basaltic clays in Victoria). Coastal sand sites can be far more stable. Your own site classification report is what counts, and the pre-slab inspection checks the work against it.
Coastal exposure
Homes near Port Phillip, Corio Bay and the Bass Strait coast face salt exposure that can corrode metal fixings, wall ties, brackets and roofing, and exposed sites can carry higher wind classifications. Where your documents specify corrosion-resistant fixings or a particular wind classification, the frame and lock-up inspections can check that what is installed appears to match.
Flooding
Parts of Greater Geelong are covered by flood-related planning controls such as the Land Subject to Inundation Overlay (example City of Greater Geelong property report). Building on land liable to flooding needs a council report and consent under regulation 153 of the Building Regulations 2018; the City of Greater Geelong assesses the location against flood studies and sets a minimum finished floor level (City of Greater Geelong). A property information certificate from council will tell you whether your land is liable to flooding (City of Greater Geelong). Where a minimum floor level applies, the pre-slab inspection can compare set-out levels with the approved drawings.
Bushfire
Some Greater Geelong land is in a designated bushfire prone area, where a Bushfire Attack Level (BAL) assessment is required and construction follows AS 3959-2018 (City of Greater Geelong). One rule has changed: regulation 157, which required a site assessed as BAL-Low to be built to BAL-12.5, was revoked from 1 May 2026, so a site genuinely assessed as BAL-Low can now be built as BAL-Low (Building Connection; Spectrum Law). Some council pages still describe the old BAL-12.5 minimum, so go by your BAL report and permit. BAL requirements affect windows, sarking, ember protection, gaps, vents and external materials, so they are relevant from frame stage onward.
Termites
Councils may designate termite risk areas under regulation 150 (AustLII). On the former Building Commission’s statewide list, Greater Geelong is partly designated, not wholly (archived Building Commission list; Vale Pest Group summary, checked Oct 2026). Your property information certificate will say whether your lot is in a termite area (City of Greater Geelong). Regulation 151, which governs construction in termite risk areas, was substituted by the Building and Plumbing Amendment Regulations 2026 (S.R. No. 38/2026), so ask your building surveyor what termite management your permit requires and check it is shown in your documents.
Energy efficiency
Your permit drawings include an approved energy rating and specifications for insulation, glazing, and sealing. Pre-plaster is the last practical point at which to compare the installed insulation with that specification.
When Should You Book Each Construction Stage Inspection?
Book the full set when you sign your building contract, then confirm each date as the build progresses. Builders’ schedules move with the weather, trades, and materials, and the pre-slab and pre-plaster windows, in particular, can close quickly.
Two practical steps make timing much easier. First, check your contract allows you or your inspector reasonable access to the site at each stage, and agree in writing how you will be notified. Second, ask your site supervisor for a heads-up a few days before each milestone.
|
Stage |
Ask your builder for |
Book when |
The window closes when |
|
1. Pre-slab |
Planned pour date |
Steel, membrane and termite measures are installed |
Concrete is poured |
|
2. Frame |
Frame completion and surveyor’s frame inspection dates |
Frame and trusses are installed and braced |
Wall wrap and cladding cover the frame |
|
3. Lock-up / pre-plaster |
Plasterboard delivery or fixing date |
Cladding, windows, roof, rough-in and insulation are in |
Plasterboard is fixed |
|
4. Fixing |
Waterproofing and tiling dates |
Plaster, joinery and wet-area work are done or under way |
Painting, final fit-off and screens finish the surfaces |
|
5. Practical completion |
Notice of completion and handover date |
You receive the completion notice |
You make final payment and accept handover |
Keep payment and inspection timing linked where you can. Before each progress payment, CAV advises checking the work has passed the building surveyor’s inspection, meets contract requirements and is complete (CAV). An inspection a day or two before the payment falls due gives you time to read the report and raise items.
What Should You Do If an Inspection Identifies Defects?
A report with items in it is normal on a new build. The goal is to get each item understood, resolved and recorded, without damaging the working relationship or your legal position.
- Read the report promptly. Note which items the inspector rates as more significant and which affect concealment at the next stage.
- Ask questions early. If an item is unclear, ask your inspector what was observed and what document or requirement it relates to.
- Send the report to your builder in writing. Email it to your site supervisor or the builder’s nominated contact, and ask for a written response on each item by a reasonable date.
- Copy your building surveyor on compliance items. Where an item relates to the permit or regulations, the surveyor can consider it and can direct the builder to fix non-compliant work (BPC).
- Ask for evidence of rectification. Photos, a revised engineering detail or a re-inspection, especially where work is about to be covered.
- Keep a running log. Item, date raised, builder’s response, date resolved and supporting photos. One spreadsheet or document is enough.
- Get advice before withholding money. CAV advises not to withhold a progress payment because of defects if the stage is complete, and to get legal advice before withholding any payment (CAV).
- Escalate if needed. If you cannot resolve an issue directly, the BPC offers free dispute resolution for eligible domestic building disputes and can issue a binding dispute resolution order or a certificate to take the matter to VCAT. For contracts signed on or after 1 July 2026, Home Warranty insurance applies if the builder becomes insolvent.
Tone helps. Most builders respond better to a specific, photographed item with a reference than to a general complaint. A well-written independent report does much of that work for you.
Do You Need All Five Construction Stage Inspections?
None of the independent inspections is legally required. Whether you book all five depends on your budget, your project and how much risk you are comfortable carrying into concealed work.
If you are choosing selectively, prioritise by what becomes hardest to see:
- Pre-slab and pre-plaster cover the most concealed work. Problems found later in the slab or behind the walls are usually the most disruptive to investigate.
- Frame is valuable on complex designs, upper storeys, large openings, steel beams or exposed sites, where the structural load path is less straightforward.
- Fixing matters most if you want wet-area work and internal finishes reviewed before painting and final fit-off.
- Practical completion is the inspection most owners book, because it is the last chance to raise items before final payment.
Some situations favour the full set: a first build, a custom or architect-designed home, a sloping or reactive site, a bushfire-prone or coastal location, or an owner who cannot visit site often. Equally, an owner with building experience on a straightforward volume-builder design may choose fewer.
For current pricing, see Ripple’s inspection cost guide or request a quote for your build.
Book Independent Construction Stage Inspections With Ripple Building Inspections
Ripple Building Inspections provides independent construction stage inspections for new homes across Geelong and Melbourne’s metropolitan suburbs, from pre-slab to practical completion. Each inspection is checked against your approved documents, and you receive a photographic report within 24 hours, so you can raise items with your builder before the next stage covers them.
Our inspections work alongside your building surveyor’s mandatory inspections; they do not replace them.
Tell us your build stage and expected dates, and we’ll help you schedule the inspections that suit your project.
Building a New Home in Geelong or Melbourne?
Don’t wait until defects are hidden behind walls or finished surfaces. Book an independent construction stage inspection and identify potential issues before your build moves to the next stage.
Frequently Asked Questions
Practical completion is the industry term for when a builder considers a home substantially finished. It has no fixed meaning for Victorian homeowners, and Consumer Affairs Victoria recommends replacing it in contracts with “complete in accordance with the plans and specifications”. For a new home, completion means the contracted work is finished to the agreed standard, major defects are fixed and the occupancy permit has been issued.