New Home Building Defects and Disputes in Victoria: Your Options

Quick answer: If you find a defect in your newly built Victorian home, record it with dated photos, check your contract and approved plans, and notify your builder in writing. If the cause is unclear, get an independent building defects report. If the builder will not fix it, BPC dispute resolution is usually the next step before VCAT. Contracts signed from 1 July 2026 may also be covered by Home Warranty.

building and timber pest inspection

Key Takeaways

  • A visible problem in a new home is a defect only when it falls short of the contract, the statutory warranties, building requirements or recognised workmanship tolerances.
  • A building defects report gives you an itemised, photographed record, but it does not by itself prove your builder is legally liable.
  • You must take reasonable steps to resolve the issue with your builder within the last 3 months before applying for BPC dispute resolution.
  • Many owner disputes need a BPC certificate of conciliation before they can go to VCAT.
  • From 1 July 2026, the BPC can issue Rectification Orders, and Home Warranty insurance applies to eligible new contracts.
  • Which code, Guide and insurance scheme apply depends on when your contract was signed and when work started.

Found Building Defects in Your Victorian Home?

You moved into your new home a few months ago. After a heavy downpour, you notice water staining the plasterboard below a bedroom window. A hairline crack has also appeared above the laundry doorway, and part of the hallway floor feels uneven underfoot.

A visible problem does not automatically prove defective construction. Whether the work is defective depends on your contract, the approved plans, the building standards that applied and how the problem developed.

An independent building defects report documents what is actually there. It gives you and your builder a clear, itemised record to work from.

Victoria offers several routes when defects are not fixed. These include a written rectification request to your builder, Building and Plumbing Commission (BPC) dispute resolution, regulatory orders, applicable insurance and, in some cases, VCAT proceedings.

What should you do first? Record the problem with dated photos, find your contract and approved plans, and notify your builder in writing. Then decide whether an independent inspection would help clarify the issue.

Table of Contents

What Is Considered a Building Defect in a New Victorian Home?

In a newly built home, a building defect is work carried out under your building contract that does not meet what was required of it. In Victoria, that requirement can come from four places:

  • The contract: the signed plans, specifications and agreed variations.
  • The statutory warranties: the implied warranties in the Domestic Building Contracts Act 1995, such as work being carried out in a proper and workmanlike manner and in accordance with the law (Consumer Affairs Victoria).
  • Building requirements: the Building Act 1993, the Building Regulations 2018, the National Construction Code (NCC) and the Australian Standards it references.
  • Workmanship benchmarks: recognised tolerances, such as those in Victoria’s Guide to Standards and Tolerances.

A defect is measured against one of these benchmarks. A problem you dislike is not always a defect, and a problem that looks minor can still breach a requirement.

This guide focuses on new homes built under a domestic building contract. For defects in established homes, including pre-purchase findings, see our guide to building defects in Victoria.

Structural defects versus non-structural defects

Structural defects affect the parts of the building that carry loads or keep it stable. Examples include excessive foundation movement, undersized or poorly connected framing members, and significant cracking in slabs or masonry.

Non-structural defects affect finish, function or appearance. Examples include uneven paint finishes, misaligned doors and cabinetry, and drummy or lipped floor tiles.

The term “major defect” can have a specific legal meaning. Under Victoria’s Home Warranty scheme, for example, major defects may include structural, waterproofing and weatherproofing defects, which attract a longer cover period. A serious-looking problem is not automatically a “major defect” for insurance purposes. That classification depends on the scheme and the assessment.

Incomplete work, defective workmanship and maintenance issues

These three categories are often confused:

  • Incomplete work is work the contract required that has not been done. A missing balustrade, an unconnected downpipe or an unfinished splashback are examples.
  • Defective workmanship is work that has been done but not to the required standard. A shower that pools water away from the floor waste is an example.
  • Maintenance issues arise from use, wear or lack of upkeep. Blocked gutters, perished silicone after several years and garden beds built up against weep holes usually fall here.

Can a defect appear after handover?

Yes. Some defects only show up once the home is occupied and exposed to weather and daily use. Moisture penetration around windows may only appear in driving rain. Drainage problems may only show after the first wet season. Progressive movement in footings can take months to produce visible cracking.

This is why the date you first noticed a problem matters. Record it.

Defect type

Examples

What homeowners might observe

Further investigation that may be needed

Structural

Footing movement, framing deficiencies, slab cracking

Diagonal cracks above doors, sticking doors, sloping floors

Comparison with engineering drawings; structural engineer assessment; crack monitoring over time

Waterproofing

Failed shower membrane, poor floor falls

Swollen skirting, mould, loose tiles, staining next to the bathroom

Moisture readings; review of waterproofing certificate; invasive testing if required

Weatherproofing

Missing window flashings, poorly sealed wall penetrations

Water staining below windows after rain, damp plaster

Check of installation against manufacturer details and approved drawings; water testing

Drainage

Incorrect site grading, unconnected stormwater

Water pooling against walls, damp subfloor, erosion

Review of stormwater plan and legal point of discharge; levels check

Workmanship

Uneven tiling, poor paint finish, misaligned fixtures

Visible lips, patchy paint, gaps at joinery

Comparison with the Guide to Standards and Tolerances and contract specifications

Incomplete work

Missing items in the contract scope

Unfinished items at handover

Comparison of completed work against the contract and plans

What Building Standards Apply to Residential Defects in Victoria?

In Victoria, the Building Act 1993 and the Building Regulations 2018 give legal effect to the National Construction Code (NCC). The Domestic Building Contracts Act 1995 sits alongside them and sets the builder’s contractual obligations and implied warranties.

The edition of the NCC that applies to your home depends on timing. NCC 2022 became mandatory in Victoria on 1 May 2023, with its energy efficiency, condensation and livable housing provisions starting on 1 May 2024. Victoria then adopted NCC 2025 on 1 May 2026, subject to transitional arrangements for designs already substantially progressed.

In practice, an inspector checks your building permit, the date of the permit application and the approved documents before deciding which edition and which referenced standards apply. The clause references below are from NCC 2022, which applies to most homes completed in Victoria between 2023 and 2026.

For ordinary detached houses (Class 1 buildings), the relevant volume is NCC Volume Two, which relies on the ABCB Housing Provisions for its deemed-to-satisfy construction details.

Foundations, slabs and structural movement

Residential slabs and footings are commonly designed to AS 2870Residential slabs and footings. The design starts with a site classification, which describes how reactive the soil is to changes in moisture. An engineer then designs the slab or footing to suit that classification.

Cracking needs context. An inspector looks at where the crack is, its pattern and width, whether it is growing and what might be causing it. A fine shrinkage crack in a garage slab is very different from a diagonal crack running from a window corner that widens over months. Not every concrete crack is a structural defect, and some cracking is expected as concrete cures.

Bathroom waterproofing and moisture ingress

For houses designed under NCC 2022, the wet area provisions are in Volume Two, Part H4, including H4D2 and H4D3. These point to Part 10.2 of the ABCB Housing Provisions or to AS 3740Waterproofing of domestic wet areas, as summarised in the BPC’s waterproofing guidance for wet areas.

The details matter. For example, the Housing Provisions require a shower floor waste with a fall between 1:80 and 1:50, and bond breakers at wall and floor junctions where membranes are bonded. Poor membrane termination, failed junctions and inadequate falls can all let water into framing and adjoining rooms.

Visible symptoms such as swollen skirting or loose tiles do not prove which part of the system failed. Moisture readings, a review of the waterproofing documentation and sometimes invasive investigation are needed to establish the cause.

Framing, masonry and weatherproofing

Timber-framed houses are commonly designed to AS 1684Residential timber-framed construction. Masonry in small buildings is commonly designed to AS 4773 Masonry in small buildings. Engineered elements such as steel beams or engineered timber follow the structural engineer’s drawings.

This means an inspector compares what is built with the approved structural details, not with a generic rule. Bracing, tie-downs, lintels and wall ties are typical items to check before they are concealed.

Windows and external walls are a frequent source of complaints. Water entry may come from missing or poorly lapped flashings, sill details, sealant failures or wall wraps that do not drain correctly. The window manufacturer’s installation instructions and the approved drawings are both relevant.

Victoria’s Guide to Standards and Tolerances

The Guide to Standards and Tolerances provides benchmarks for assessing domestic workmanship. The 2026 Guide applies prospectively from 1 August 2026. It does not apply retrospectively to contracts entered into or work commenced before that date, which are assessed against the previous version.

The Guide is not legislation. It does not replace the NCC, Australian Standards or your contract, and where those set a specific requirement, that requirement takes precedence.

Two examples show how it is used:

  • Appearance: A patch of uneven paint finish on a living room wall is usually assessed by viewing it from a normal position in normal light. The Guide helps decide whether it falls within an acceptable tolerance.
  • Potentially significant defect: Water staining below a window is not a cosmetic matter. It points towards possible weatherproofing failure, which is assessed against the NCC, the manufacturer’s details and the approved drawings rather than an appearance tolerance.

Technical defect-reference matrix

Use this matrix as a starting point for conversations with your builder or inspector. A symptom in the last column is a reason to investigate, not proof of a breach.

Defect category

Applicable codes or standards (typical)

Relevant construction documents

Possible inspection observations

Footings and slabs

AS 2870; NCC Volume Two; ABCB Housing Provisions

Soil or geotechnical report; site classification; engineer’s footing and slab design

Cracking pattern and width, uneven floors, sticking doors, changes over time

Wet area waterproofing

NCC 2022 Vol Two H4D2, H4D3; Housing Provisions Part 10.2; AS 3740

Waterproofing certificate; wet area details; tile and membrane specifications

Moisture readings near showers, falls to waste, loose or drummy tiles, swollen skirting

Timber framing

AS 1684 or engineer’s design

Approved structural drawings; bracing and tie-down schedules; truss layouts

Missing straps or bracing, notched members, framing out of plumb

Masonry

AS 4773 or engineer’s design

Approved elevations and structural details; lintel schedule

Cracked brickwork, missing or blocked weep holes, lintel bearing issues

Windows and external walls

NCC Volume Two weatherproofing provisions; manufacturer’s installation instructions

Window schedule; wall wrap and flashing details

Staining below sills, missing head flashings, gaps in sealant

Site drainage

NCC Volume Two; plumbing requirements; council legal point of discharge

Approved stormwater plan; legal point of discharge report

Ponding against walls, unconnected downpipes, ground sloping towards the house

How to Read a Building Inspection Sample Report

What Is a Building Defects Report?

A building defects report is a documented assessment of observed defects or suspected defective work in a newly built home, prepared within an agreed inspection scope. It records what the inspector saw, where it is, how significant it appears and what should happen next.

Its main value is independence. When you and your builder disagree about the condition of the work, a report from an independent inspector replaces “he said, she said” with specific, photographed and located observations. Builders tend to respond better to a clear, itemised list than to general complaints.

 

What should a building defects report include?

A useful report generally covers:

  • Property and inspection details: address, date, weather, who attended and what areas were accessed.
  • Scope and limitations: what was inspected, what was not and why (for example, no roof access or furniture covering floors).
  • Description and location of each defect: a specific room, elevation or grid reference.
  • Photographic evidence: wide shots for context and close-ups for detail.
  • Relevant measurements and observations: for example, moisture readings, level readings or crack widths.
  • Reference to applicable requirements: where the inspector can establish them, such as a clause of the Housing Provisions or a tolerance in the Guide.
  • Assessment of significance: whether the item appears minor, significant or a safety concern, and whether further investigation is needed.
  • Recommendations or next steps: within the inspector’s competence, such as referral to a structural engineer or plumber.

Each issue should be individually numbered and identifiable. That way you, your builder and any later assessor can refer to “Item 7” without confusion, and you can track which items have been fixed.

What a building defects report cannot establish on its own

Most defects reports are based on a visual, non-invasive inspection. That has limits:

  • Concealed problems inside walls, under slabs or beneath tiles may not be visible.
  • A visual inspection may not conclusively establish what caused damage.
  • A report does not, by itself, establish who is legally liable.
  • It does not guarantee a particular outcome in a dispute.
  • It does not replace a structural engineer’s report, a plumber’s investigation or legal advice where those are needed.

A good report says what it can and cannot conclude, and recommends specialist input where the evidence runs out.

Building Defects Report vs Handover, Warranty and Expert Reports

Inspection reports are written for different purposes. The right one depends on where your build is up to and what you need the report to do.

Report type Purpose Typical timing Limitations
Construction stage inspection Check work before it is covered up Base, frame, lock-up and fixing stages Records conditions at one point in time; later work can change things
Practical completion or handover inspection Identify defects and incomplete work before you accept the home Before final payment and handover Some defects only appear after occupation and weather exposure
Post-handover building defects report Document defects that appear or persist after you move in Any time after handover, ideally soon after a problem appears Visual and non-invasive unless agreed otherwise
Builder's warranty inspection Record outstanding items before a contractual defects or maintenance period ends Shortly before the period expires Limited to items observable on the day
Section 137B owner-builder defects report Meet the Building Act 1993 requirement before an owner-builder sells a home they built Before sale of owner-built work within the statutory period Serves a sale-disclosure purpose; not designed as dispute evidence
Dilapidation report Record the existing condition of a property before nearby works Before demolition, excavation or construction next door Records condition only; does not assess the quality of your own build
Specialist expert witness report Provide opinion evidence for VCAT or court During formal proceedings Must meet tribunal procedural requirements; usually prepared by a qualified expert in the relevant field
Understanding Section 137B reports

A Section 137B report serves a particular Victorian purpose: an owner-builder selling the property must provide a defects report to the purchaser. It is not automatically the same as a report commissioned for a dispute with a builder, even though both describe defects.

Expert evidence for VCAT proceedings may need more than a standard inspection report. The expert may need particular qualifications, may need to acknowledge duties to the tribunal and may need to follow VCAT's practice requirements for expert evidence. Ask your lawyer what is needed before commissioning a report for that purpose.

How to Document Defective Building Work Before Contacting Your Builder

Good records make every later step easier. Follow this sequence:

  1. Record when and where the problem was first identified. Note the date, the room and what you saw.
  2. Take clear photographs. Take one wide shot to show the location, then close-ups. Repeat over time if the issue is changing.
  3. Record observations without altering the area. Do not remove tiles, cut plaster or reseal joints before the issue has been inspected.
  4. Locate your contract documents. Find the signed building contract, variations and the approved plans and specifications.
  5. Gather prior reports and correspondence. Include stage inspection reports, the handover report and emails or messages with the builder.
  6. Obtain an independent defects assessment where appropriate. This is especially useful where the cause or significance is unclear.
  7. Give the builder a clear written defect schedule. List each item separately and ask for a response by a reasonable date.
  8. Keep written records of every response. Record proposed repairs, agreed dates and what was actually done.

Chronological records matter because the BPC expects you to show reasonable attempts to resolve the dispute, and Home Warranty claims for defects must be made within 12 months of when you became aware of the issue.

Safety first: If you suspect an urgent electrical, gas, structural or other hazard, contact an appropriately qualified professional or emergency service immediately. Documentation can wait; safety cannot.

Example defect schedule

Defect ID

Location

Observed issue

Evidence

Relevant document or requirement

Requested response

Status

D01

Bedroom 2, north window

Water staining to plaster below sill after rain

Photos 1 to 4; dated notes

Window schedule; flashing detail on approved drawings

Investigate source and rectify

Awaiting builder response

D02

Ensuite shower

Water pooling away from floor waste

Photos 5 to 6; video

Housing Provisions Part 10.2 falls to waste

Inspect falls and rectify

Reported

D03

Laundry doorway

Diagonal crack in plaster above door frame

Photos 7 to 8; crack width recorded weekly

Engineer’s footing design; site classification

Assess cause; advise remedy

Monitoring

Hypothetical example: water entering around a window in Greater Geelong

This is an illustrative scenario, not a Ripple Building Inspections project.

A homeowner in a new estate in Greater Geelong moves in during summer. In early winter, after a night of heavy rain and strong south-westerly wind, they notice a damp patch and water staining on the plasterboard below a bedroom window.

  1. Document: They photograph the stain that morning, note the date and weather, and photograph the outside of the window. They do not remove the sill trim.
  2. Identify the documents: They find the window schedule and the wall section details in the approved drawings. They also find the window manufacturer’s installation guide.
  3. Notify the builder: They email the builder with photos and a single-item defect schedule, asking for an inspection within a reasonable time.
  4. Seek an inspection: The builder suggests the problem is a blocked weep hole caused by the owner. The homeowner arranges an independent inspection. The inspector records moisture readings around the window, observes the external flashings and sill, and recommends a water test by a suitably qualified person to identify the entry point.
  5. Pursue rectification: The homeowner sends the report to the builder and asks for a written proposal to investigate and fix the cause. If the builder declines, the homeowner keeps all correspondence and considers BPC dispute resolution, as explained below.

Homeowner documentation checklist

Assemble these before seeking dispute resolution:

  • Signed building contract, including general conditions
  • All signed variations
  • Approved plans, specifications and engineering drawings
  • Building permit and documents referenced in it
  • Records of mandatory inspections by the building surveyor
  • Occupancy permit (new home) or certificate of final inspection (renovation)
  • Certificate of insurance (DBI) or Notice of Cover (Home Warranty)
  • Stage, handover and defects inspection reports
  • Dated photographs and videos of each defect
  • Your defect schedule and the builder’s responses
  • Emails, letters and text messages with the builder
  • Invoices and payment records
  • Quotes from other trades for rectification, if obtained
  • Any specialist reports (engineer, plumber, electrician)

What If Your Builder Disagrees With the Defects Report?

Disagreement is common. A builder may accept that a problem exists but dispute its cause, its severity or who is responsible. Keep the discussion focused on evidence:

  • Ask for the technical basis. Request that the builder identify the contract clause, drawing or standard that supports their position.
  • Check the approved plans and specifications. The answer is often in a detail you already have.
  • Compare the issue with the applicable standards. Use the code edition and Guide version that apply to your contract date.
  • Get specialist advice where needed. A structural engineer, licensed plumber or other specialist can resolve technical disagreements a general inspection cannot.
  • Give the builder a reasonable opportunity to respond. Set a clear, reasonable deadline in writing.
  • Record any agreement. If the builder agrees to fix an item, confirm the scope, method and timing in writing.

Factual inspection evidence is useful because it identifies the actual issue, its location and its extent. That shifts the conversation from competing opinions to what is physically there.

Be careful with drastic steps. Do not withhold payments, terminate the contract or commission irreversible repairs by another trade without first considering your contract and getting legal advice. These steps can affect your rights, your builder’s obligations and any later insurance claim. The Domestic Building Legal Service offers advice to Victorian homeowners in disputes with builders (Consumer Affairs Victoria).

2026 Regulatory Update: What Has Changed in Victoria

Victoria's domestic building system changed significantly in mid-2026. Which rules apply to you depends on when your contract was signed and when work started.

Change Start date What it means for homeowners Source
BPC manages domestic building dispute resolution In place Formerly DBDRV The free conciliation service previously known as Domestic Building Dispute Resolution Victoria is now run by the Building and Plumbing Commission. BPC
Rectification Orders 1 July 2026 BPC may order responsible parties to fix or complete defective, incomplete or non-compliant work, up to 10 years after the relevant completion milestone. BPC
Home Warranty insurance 1 July 2026 Contracts signed on or after this date First-resort protection for eligible work over $20,000, up to $400,000 per home, replacing DBI for new contracts. BPC
Guide to Standards and Tolerances 2026 1 August 2026 Contracts entered into or work commenced from this date Updated workmanship benchmarks; earlier contracts use the previous Guide. BPC

Domestic Building Dispute Resolution in Victoria: Step-by-Step

The BPC offers a free and impartial dispute resolution service for domestic building disputes. It was previously known as Domestic Building Dispute Resolution Victoria (DBDRV), and existing cases continue to be managed by the BPC. Applications involving health, safety or financial hardship are prioritised.

Step 1 Attempt to resolve the issue directly

You must first try to resolve the dispute with the builder yourself. The BPC requires that you have taken reasonable steps within the last 3 months, including clearly stating your concerns (preferably in writing) and giving the builder a reasonable time to respond.

At a minimum, that means multiple attempts to contact the builder, engaging with them if they are willing, and preferably telling them you intend to apply. Keep copies of every attempt.

Step 2 Check whether the dispute is eligible

Eligible disputes must concern domestic building work and must involve the building owner. They can cover defective or incomplete work, delays, payment issues and contract issues.

Some disputes are not eligible. A dispute about only one type of work under a standalone contract, such as a painting-only or tiling-only contract, may be ineligible. If that same work formed part of a broader contract, it may be eligible, as the BPC's eligibility scenarios explain. Disputes about commercial work, matters already before VCAT or a court, and work more than 10 years old are also generally excluded.

Step 3 Submit an application and supporting documents

Once you apply, you receive a dispute reference number. The BPC then checks whether the dispute is within its jurisdiction.

Before conciliation, you may be asked for your contract, plans and specifications, the building permit and approved documents, building surveyor inspection records, variation and extension of time requests, relevant correspondence and your occupancy permit or certificate of final inspection. Your defects report and photographs help explain each item.

Step 4 Assessment and conciliation

A Dispute Resolution Officer (DRO) assesses whether the dispute is suitable for conciliation, considering the steps already taken and the likelihood that conciliation will help.

The BPC may arrange a building assessor to examine the disputed work. Assessors determine whether work is defective or incomplete, may identify the cause and provide a timeframe for rectification. Both parties receive the assessment report afterwards and have 5 business days to raise concerns. There is generally no fee for an assessment.

Conciliation is then facilitated by a conciliator, by video, phone, onsite or at the BPC's office. All parties with authority to resolve the dispute must attend.

Step 5 Understand the possible outcomes
Record of agreement

If the parties agree, the DRO records the agreed actions, payments and timelines.

Dispute resolution order

A binding order the BPC may issue if the dispute is unresolved, partly resolved or an agreement is not honoured.

Certificate of conciliation

Issued where a dispute is unsuitable for conciliation or is not resolved and an order is not appropriate. This certificate enables either party to apply to VCAT. See the BPC's guide to conciliation outcomes.

The appropriate outcome depends on the facts of the dispute and the statutory process. Neither party is guaranteed a particular result.

When can a dispute proceed to VCAT?

Most owner disputes reach VCAT only after BPC dispute resolution produces a certificate; a dispute resolution order can be reviewed by VCAT in limited circumstances.

What Is a Rectification Order in Victoria?

A Rectification Order is a formal order from the BPC requiring building work to be fixed or completed. It may be used where work is incomplete, defective or non-compliant, and is one of several regulatory tools the BPC can use from 1 July 2026.

The power has a long reach. The BPC can issue a Rectification Order up to 10 years after the certificate of final inspection, the occupancy permit, or practical completion for work that did not need a building permit. An order may be issued to the builder, a subcontractor, a developer or another person the BPC considers responsible.

It is easy to confuse three similar-sounding tools:

Tool

Where it comes from

What it generally concerns

Direction to Fix

Building surveyor or regulatory compliance powers

Non-compliant work identified during construction

Dispute Resolution Order

BPC domestic building dispute resolution process

A binding order between the parties after conciliation does not fully resolve a dispute

Rectification Order

BPC regulatory power from 1 July 2026

Requiring responsible parties to rectify or complete defective, incomplete or non-compliant work

A Rectification Order is not automatic. The BPC assesses each matter and decides what action, if any, is appropriate. Where Home Warranty is not available, it prioritises serious matters involving a major building element, such as work that makes a home uninhabitable, threatens collapse or risks death or serious injury.

The BPC expects you to have raised the issue with your builder first. It may ask for more information, arrange an inspection or direct the parties to dispute resolution instead. A private inspection report can support your request, but it does not entitle you to an order.

When Can You Take a Building Dispute to VCAT?

The Victorian Civil and Administrative Tribunal (VCAT) hears domestic and commercial building disputes between owners, builders, subcontractors and other building practitioners. It also hears disputes between owners and warranty insurers. VCAT can also review certain BPC decisions, such as a dispute resolution order.

For many eligible domestic building disputes involving an owner, a vcat building dispute cannot start straight away. You generally need to go through the BPC dispute resolution process first and obtain a certificate of conciliation, unless an exception applies. Disputes outside the BPC's service, such as a single-trade standalone contract, may go directly to VCAT. Check VCAT's current guidance on applying in a building and construction dispute before you lodge.

Evidence that may be relevant includes:

  • signed contracts and variations
  • approved drawings and specifications
  • defects reports and BPC assessment reports
  • specialist assessments, such as engineering reports
  • dated photographs and video
  • relevant correspondence with the builder
  • quotations for rectification work
  • records of previous dispute resolution attempts and certificates

Tribunal proceedings can involve filing fees, directions hearings, compulsory conferences or mediation, expert evidence requirements and a final hearing. Legal and expert costs can be significant. Check VCAT's current fees and timeframes at the time you apply rather than relying on older figures.

Get legal advice if your dispute is complex, involves a large sum or may be approaching a limitation period. Time limits for building actions can be strict.

Who does what: government authorities and inspectors compared

Scroll horizontally to view all columns.

Organisation Inspects Regulates Certifies Facilitates dispute resolution Adjudicates claims
Building and Plumbing Commission Yes, through assessors and compliance inspections Yes, practitioners and building work No (registers practitioners) Yes, conciliation and dispute resolution orders No; decides insurance claims and regulatory action, not legal liability between parties
Relevant building surveyor Yes, mandatory inspections at prescribed stages Enforces permit compliance on the project Yes, building permits, occupancy permits, certificates of final inspection No No
City of Greater Geelong Limited, for council permits and its own infrastructure Planning scheme, local drainage and municipal building functions Issues building permits when engaged as surveyor; legal point of discharge reports No No
VCAT No No No Offers mediation and compulsory conferences Yes, makes binding decisions on building disputes
Independent building inspector Yes, as engaged by the owner No No No No; provides evidence and opinion only

Who Pays to Fix Building Defects in Victoria?

In most cases, the builder is responsible for fixing defective or incomplete work it carried out under the contract. Who actually pays depends on the contract, the statutory warranties, the cause of the defect and whether any insurance applies.

A defect, a warranty claim and an insurance claim are different things. A defect is the problem in the building. A warranty claim is a claim against the builder. An insurance claim is a claim against the insurer or scheme, which only applies in specific circumstances.

Statutory building warranties

The Domestic Building Contracts Act 1995 implies warranties into every domestic building contract. They require, among other things, that work is carried out in a proper and workmanlike manner, in accordance with the plans and specifications and the law, with good and suitable materials, and that a new home is suitable for occupation (Consumer Affairs Victoria).

These warranties apply regardless of cost and cannot be signed away. They also transfer to subsequent owners for up to 10 years from completion of the work (Consumer Affairs Victoria). This aligns with the general 10-year limitation framework for building actions in the Building Act 1993.

The 10-year warranty period is not an insurance cover period. Insurance runs for shorter periods, explained below.

Domestic Building Insurance for earlier contracts

Domestic Building Insurance (DBI) applies to work under contracts signed before 1 July 2026 where a certificate of insurance was issued. It was required for work over $16,000.

DBI is "last resort" cover. It generally responds only if the builder has died, disappeared or become insolvent. Policies issued on or after 1 July 2015 also respond if the builder fails to comply with a VCAT or court order (Consumer Affairs Victoria).

Home Warranty insurance from 1 July 2026

Home Warranty applies to eligible domestic building contracts signed on or after 1 July 2026. Key features:

  • It applies to eligible work valued at more than $20,000.
  • It can cover new homes, alterations and extensions, residential buildings up to three storeys containing more than two homes, and some pool work.
  • It is "first resort": it may assist where eligible work is incomplete, defective or non-compliant and the builder fails or refuses to fix it, not only when the builder has died, disappeared or become insolvent.
  • Maximum assistance is $400,000 in total per home, subject to eligibility, limits and exclusions.
  • It does not cover minor cosmetic differences, and it does not protect owners who use an unregistered builder for work requiring a registered builder.

Existing DBI policies do not convert to Home Warranty; they continue on their existing terms.

Scroll horizontally to view all columns.

Feature Domestic Building Insurance (DBI) Home Warranty
Applies to Contracts signed before 1 July 2026 with a DBI certificate Eligible contracts signed on or after 1 July 2026
Work value threshold Over $16,000 Over $20,000
Type of cover Last resort First resort
Main triggers Builder death, disappearance or insolvency; failure to comply with a VCAT or court order (policies from 1 July 2015) Builder fails or refuses to complete or fix eligible defective, incomplete or non-compliant work; insolvency and similar events
Maximum cover Generally up to $300,000 Up to $400,000 in total per home
Cover period for defects 6 years structural, 2 years non-structural Up to 6 years for major defects; up to 2 years for other defects
Incomplete work cap May be limited to 20% of the contract price Capped at 30% of the total contract price
Claim timing for defects Per policy terms Within 12 months of becoming aware of the issue

Sources: BPC: DBI and Home Warranty, BPC: Home Warranty time limits and amounts, Consumer Affairs Victoria.

Not every defect is insured, and the BPC does not automatically pay for repairs. Eligibility, claim timing, limits and exclusions all apply.

Building Defects in Geelong: Local Conditions and Construction Requirements

New homes in Greater Geelong are built under the same Victorian legislation and NCC requirements as homes in Melbourne. What differs is the site. Soil, drainage, coastal exposure and bushfire risk vary across the municipality, and each property's approvals set out which additional design requirements apply. When investigating a defect in Geelong, these four local factors often matter.

Site classification and foundation movement

If you notice cracking, sticking doors or uneven floors, start with the soil or geotechnical report, the site classification, the structural engineer's drawings and the approved footing design. These tell you how reactive the soil was assessed to be and how the slab or footings were designed to cope with it.

Do not assume your soil is the same as a neighbour's or a nearby estate's. Soil conditions can vary significantly across Greater Geelong, and even within one estate. A crack only makes sense once it is compared with the design for that specific lot.

A legal point of discharge (LPoD) is where stormwater from a private property is permitted to discharge, usually into the council drainage system or road reserve. In Greater Geelong, property owners are responsible for their private stormwater system up to and including the LPoD, and the City is responsible for its own infrastructure from that point (City of Greater Geelong).

Example: After heavy rain, water pools against the rear wall of a new home and the plaster inside starts to show damp marks near the floor. An inspection may need to consider the finished ground levels and grading away from the house, whether every downpipe is connected, whether drains are connected to the approved LPoD, and whether the work matches the approved stormwater plan. A licensed plumber may be needed to investigate below-ground drainage.

Coastal exposure and external building materials

Homes near the coast, Corio Bay or other corrosive environments may need materials with higher corrosion protection. That can affect roof sheeting, fixings, lintels, brick ties, balustrades and window hardware.

The requirement depends on a site-specific exposure assessment, not the suburb name. When investigating premature rust or deterioration, check what exposure classification and corrosion protection were specified in the approved documents, and whether the installed products match. Not every Geelong suburb has the same exposure classification.

Bushfire-prone areas and construction compliance

Some land in Greater Geelong is within a designated Bushfire Prone Area, some is within the Bushfire Management Overlay, and some is subject to both (City of Greater Geelong). You can check your property with a VicPlan planning property report.

New homes and alterations in a Bushfire Prone Area must be constructed in accordance with AS 3959 Construction of buildings in bushfire-prone areas. A Bushfire Attack Level (BAL) assessment at the building permit stage determines the construction requirements, from BAL-LOW to BAL-FZ (City of Greater Geelong).

If your home has a BAL rating, an inspection can compare completed elements with the approved BAL requirements. Typical items include ember screening to vents and weep holes, glazing, external door and window frames, sarking, gaps at roof junctions and the materials used for decks and cladding.

For permit-related questions, see the City's building permits information.

When Should You Arrange an Independent Inspection?

Timing affects what an inspector can see and what you can do with the findings. Consider an independent inspection:

  • Before structural elements are concealed. Frame-stage issues are far easier to identify and fix before plaster goes on. See New Home Construction Stage Inspections.
  • Before handover or completion. This is your best chance to have items fixed before final payment. See Handover Practical Completion Inspections.
  • When significant problems arise after you move in. Leaks, cracking and drainage problems are worth documenting early.
  • Before a contractual defects liability or maintenance period ends. See Builder's Warranty Inspections.
  • When a builder repeatedly declines to address reported issues. An itemised report can reset the conversation.
  • When preparing documentation for a formal dispute. A clear report supports a BPC application.

Mandatory inspections and independent inspections are different. The relevant building surveyor carries out mandatory inspections at prescribed stages to check compliance with the building permit. Those inspections are not designed to identify every workmanship issue on your behalf. An inspector you engage works for you and can look at quality and finish as well as visible compliance issues, within the agreed scope.

How Ripple Building Inspections Can Help Document Building Defects

Ripple Building Inspections provides independent inspections for people building new homes in Geelong and Melbourne metropolitan suburbs, from construction stages through to handover and the months after you move in. When you are dealing with a possible defect in your new home, an independent inspection can help you:

  • identify and document observed defects, each listed separately with its location
  • support each finding with photographic evidence
  • understand the practical significance of what was found
  • know when further investigation by a specialist is recommended

Our findings are written to help you communicate clearly with your builder and decide whether further investigation or advice is needed. We document what we observe within the agreed scope. We do not act as your lawyer, a dispute resolution authority or a decision-maker on liability.

Ripple also offers building and property inspections, dilapidation reports and Section 137B owner-builder defects reports.

Request an Independent Building Inspection in Geelong or Melbourne

Conclusion: From Possible Defect to a Clear Next Step

A crack, leak or uneven floor is the start of a process, not the end of one. Record the problem, find your contract and approved plans, and raise it with your builder in writing. If the cause or significance is unclear, an independent building defects report provides you with an itemised, photographic record to work from.

If the builder does not respond, Victoria provides several routes: BPC dispute resolution, Rectification Orders, Home Warranty for contracts signed from 1 July 2026, and VCAT where the process allows. Which route fits depends on your contract date, the type of defect and what has already been tried.

If you need a clear, independent record of what is happening in your home, Ripple Building Inspections can help.

Building a new home in Geelong or Melbourne?

Get an independent, itemised record of what is happening in your build.

Frequently Asked Questions

It is not legally required, but it is strongly recommended. There is no cooling-off period when you buy at auction. You also cannot add a building inspection condition after winning unless the seller agrees. An inspection completed before auction day lets you understand the property’s condition, seek specialist advice and set a realistic bidding limit before you are bound by the contract.
Yes, if cooling-off applies to your purchase. You would need the inspection done and the report reviewed within three clear business days of signing. That is a tight timeframe. Cooling-off also does not apply to auction purchases or sales within three clear business days before or after an auction. A negotiated inspection condition or an earlier inspection is usually safer.

You can ask, but the seller does not have to accept. Pre-auction offers are usually made by signing a contract, and negotiation works much like a private sale. Many sellers prefer unconditional offers before auction. If your offer is accepted less than three clear business days before the auction, there is no cooling-off period. Inspect before signing where possible.

You have options before you are committed. You can get specialist advice, obtain repair estimates, lower your maximum bid or decide not to bid. You can also ask the agent whether the seller will respond to the findings. The key advantage is that you make these decisions before the hammer falls, rather than after signing an unconditional contract.

No. Victorian law does not require buyers to get a building inspection. However, Consumer Affairs Victoria recommends getting independent expert help on building matters before bidding. Lenders may also have their own requirements. For most buyers, an inspection is a relatively small cost compared with the risk of buying a home with unexpected structural or pest problems.
Not generally. The Section 32 vendor statement discloses legal and property information, such as title details, planning controls, outgoings and certain building permits. It is not a building condition report. It will not tell you about leaks, cracking or timber pest damage. Read it alongside a building inspection report and council building records.

Yes, in a limited way. Consumer Affairs Victoria states buyers are entitled to inspect the property at any reasonable time during the week before settlement, to check it is in the condition it was sold in. A further building inspection, for example to verify agreed repairs, usually needs the seller’s agreement, ideally documented in the contract or repair agreement.

In a private sale, often yes, particularly before you sign or if your contract has an inspection condition. The seller can refuse. At auction, you can use the findings to set your bidding limit, but negotiation after winning is limited. Once the contract is unconditional, inspection findings alone generally do not give you a right to reduce the price.
The on-site inspection for a typical house often takes one to three hours. Time depends on size, age, access and whether a timber pest inspection is included. Reports from Ripple are generally available within 24 hours. Allow extra time after receiving the report for questions and specialist advice before auction day.