Practical Completion Inspection: A Complete Guide to New Home Handover
Key Takeaways
- “Practical completion” is common industry language, but Consumer Affairs Victoria recommends that new home contracts use “complete in accordance with the plans and specifications” instead.
- An occupancy permit confirms the home can be occupied. It does not confirm that every item in your contract is finished or free of defects.
- A practical completion inspection is visual. It cannot certify concealed waterproofing, plumbing, or electrical work, so certificates and earlier-stage records matter.
- Victoria adopted NCC 2025 on 1 May 2026, and the Guide to Standards and Tolerances 2026 applies from 1 August 2026. Neither automatically applies to every home being handed over this year.
- Contracts signed on or after 1 July 2026 may be covered by the new Home Warranty scheme. Earlier contracts generally remain under Domestic Building Insurance.
- Get independent legal or building advice before withholding a disputed final payment.
Your builder has sent the email. The house is “practically complete”, the walkthrough is booked, and the final claim is on its way. After months of slab pours, frame inspections and selections appointments, it is tempting to treat handover as a formality.
It is not. Handover is the last point in the build where the money, the keys and the obligation to fix things all sit in one place. What you accept on that day shapes every conversation you have with your builder afterwards.
This guide explains what practical completion means in Victoria, how it differs from the occupancy permit and contractual completion, what a practical completion inspection can and cannot check, and what to do if defects or unfinished work remain. It also covers the 2026 changes to building standards and home warranty that affect homes being handed over now.
Approaching handover? Book a practical completion inspection with Ripple Building Inspections and bring a written, photographic defect report to your final walkthrough.
Table of Contents
What Is Practical Completion in a New Home Build?
In everyday construction practice, practical completion is the point at which the builder considers the home substantially finished. The trades have left, the cleaners have been through, and the builder is ready to walk you around and hand over the keys.
The inspection carried out at this stage goes by several names. You will hear it called a practical completion inspection (PCI), a pre-handover inspection or simply a handover inspection. They all describe the same thing: a final review of the finished home before you accept it.
The difficulty is that “practical completion” has no fixed meaning for Victorian homeowners. Consumer Affairs Victoria lists the expression among terms to remove from a new home contract. Its advice is to delete it and insert “complete in accordance with the plans and specifications”. The reason is simple. “Practically complete” can be read as “nearly finished”. Your contract entitles you to a home that is finished.
Consumer Affairs Victoria describes building work as complete when two things have happened:
- all work in the contract’s plans and specifications is finished to the agreed standard and major defects have been fixed, and
- the building surveyor has issued an occupancy permit (for a new home) or a certificate of final inspection (for an extension or renovation).
Working appliances, fresh paint and a clean floor do not meet that test on their own. A home can look ready and still have a missing retaining wall, a shower that drains towards the door or a fence that was in the contract but never built.
It helps to sort what you find into three groups:
| Type of finding | Example | Why it matters |
|---|---|---|
| Minor finishing concern | Paint runs, a chipped tile, an uneven grout line | Usually quick to fix and best raised before handover |
| Incomplete contractual work | A driveway, fence or fixture shown in the contract but not installed | The work is not finished in accordance with the plans and specifications |
| Safety or compliance concern | A balustrade that looks loose, a missing smoke alarm, water escaping a shower | May affect safety, approval or how the home performs |
A practical completion walkthrough, contractual completion and occupancy approval are related, but they answer different questions. The next section separates them.
Practical Completion vs Handover vs Occupancy Permit
Several milestones cluster in the final weeks of a build. Homeowners regularly assume one covers the others.
| Milestone | Primary purpose | Responsible party |
|---|---|---|
| Practical completion inspection | Identify visible defects, incomplete work and concerns against the agreed scope | An independent inspector or consultant engaged by the homeowner |
| Building surveyor's final inspection | Assess matters under the building permit and building regulations | The relevant building surveyor |
| Occupancy permit | Authorise occupation of the new home | The relevant building surveyor |
| Contractual completion and final payment | Decide whether the required work and completion conditions in the contract are satisfied | Builder and homeowner, under the contract |
| Handover | Transfer keys, documents and possession | Builder and homeowner |
The building surveyor's role is regulatory. The surveyor inspects the work at the mandatory stages listed on the building permit and determines whether the home is suitable for occupancy. That inspection is not a review of finish quality, nor a check of your contract. A surveyor will not normally assess whether your skirting has gaps, whether your benchtop is the stone you selected or whether the garden shed in your inclusions list was ever installed.
A private building inspection works the other way. It does not replace the statutory final inspection, and it does not lead to an occupancy permit. What it gives you is independent information about workmanship, defects and unfinished items, measured against your contract documents and recognised benchmarks.
This distinction matters most for items outside the house itself. A major domestic building contract for a new home can include associated work such as driveways, paving, fencing and landscaping. Those items may sit in your contract without being needed for the home to be fit to occupy. An occupancy permit can therefore be issued while contracted external work is still outstanding.
So the occupancy permit is necessary for completion, but it is not proof of it. Treat it as one item on your checklist, not the finish line.
When Should You Book a Practical Completion Inspection?
Book once your builder gives you a proposed completion or walkthrough date. The aim is to determine when the finished areas can be properly examined, and to do so early enough for the builder to act on the report before you are asked to pay.
There is no Victorian rule requiring an independent inspection a fixed number of days before handover. The timing below is practical advice, not law.
- Inspect when the work is genuinely finished. Floor coverings laid, appliances installed, wet areas sealed, power connected and the site cleared. Inspecting half-finished rooms produces a long list of items the builder was always going to complete.
- Inspect before the builder’s walkthrough, or on the same day. Taking a written report into the walkthrough means the builder’s defect list starts from a complete picture.
- Leave time for the builder to respond. A report delivered the night before handover leaves no room to fix anything. Allowing a week or more is usually sensible.
- Read your contract. Check the notice of completion clause, the handover procedure and the final payment provisions. These set the timetable you are working to.
- Book a reinspection. Once the builder says items are fixed, have the significant ones checked again before final payment.
Victorian homeowners have a right to reasonable access to their building site during construction, including for an independent consultant. Consumer Affairs Victoria says this applies even if the contract tries to limit visits. Give the builder written notice of the inspection and coordinate with the site supervisor on safety before anyone enters the site. An inspection should support completion, not delay it.
If you have used construction stage inspections during the build, tell your inspector. Earlier reports and photos help them focus on what has changed since.
What Does a Practical Completion Inspection Cover?
A practical completion inspection examines the accessible parts of the finished home, inside and out. The inspector compares what they can see and safely operate with your contract documents and recognised workmanship benchmarks. The exact scope depends on the agreed service and on-site access on the day.
Roof, Exterior Walls and Weatherproofing
Outside, the inspector assesses the visible condition of roof coverings, ridges, valleys, gutters, downpipes, and flashings where they can be safely inspected. They check cladding and brickwork for cracking, gaps at junctions, damaged sarking or wrap left exposed, and blocked or missing weep holes. Window and door junctions, sills and seals get close attention.
A cosmetically finished exterior can still have water-management problems. Paint can look perfect over a flashing that laps the wrong way. A gutter can be neatly installed with too little fall to reach the downpipe. These are the details that decide whether water stays outside the building, and they are easy to miss from the footpath.
Bathrooms, Showers and Wet Areas
The inspector runs showers and taps to see where water goes. Common findings include floors that do not fall to the waste, ponding in shower bases, water escaping past the screen and gaps or breaks in sealant at internal corners and junctions. Grout, tile finish, drummy (hollow-sounding) tiles and any signs of moisture outside the wet area are also recorded.
The waterproofing membrane itself sits under the tiles. A completed-home visual inspection cannot fully verify it. Earlier waterproofing-stage photos, the installer’s records and any compliance certificate are better evidence that the membrane was installed correctly. Ask your builder for them. Our guide on inspecting bathroom leaks explains the warning signs that appear later.
Internal Walls, Ceilings, Floors and Joinery
Inside, the inspector records plaster cracking, poor joints, nail pops, paint coverage, gaps at cornices and skirtings, damaged or lifting flooring and scratched surfaces. Doors and windows should open, close and latch properly, with even gaps. Cabinetry, benchtops, shelving, architraves and fitted fixtures are checked for alignment, damage and completeness.
Not every visible variation is a defect. Finish quality should be judged against your contract specifications and the applicable workmanship tolerances, not against personal preference alone. A good report says which benchmark an item falls short of.
Plumbing, Drainage and Water Fixtures
The inspector checks for visible leaks under sinks and vanities, operates taps and toilets, confirms that hot water reaches the fixtures, and inspects accessible pipework and drainage fittings. Slow-draining wastes and gurgling fixtures are noted.
A visual handover inspection cannot certify concealed plumbing or confirm that all plumbing work complies. Plumbing work in Victoria is carried out by licensed or registered plumbers who issue their own compliance certificates. Where the inspector sees something that needs testing, the report should recommend a licensed plumber.
Electrical Fixtures, Ventilation and Safety
Where it is safe, the inspector operates lights, accessible switches, and power points, tests smoke alarms, and checks exhaust fans in bathrooms, laundries, and kitchens. They look for missing cover plates, damaged fittings and visible safety concerns.
These are operational checks only. Testing circuits, switchboards and wiring is work for a licensed electrician. The electrician’s certificate of electrical safety is the document that addresses compliance.
Garage, Driveway, External Drainage and Site Works
The inspector operates the garage door and checks for safety features such as auto-reverse, where fitted. They walk the accessible paving, paths, and driveway, look at how the ground falls around the house, and note any ponding, disconnected downpipes, exposed stormwater pipes, or open pits. Retaining walls, fencing and other external items are compared with what the contract includes.
Driveways, fences, and landscaping are common sources of handover disputes. They may be contractual completion items even when they are not needed for the occupancy permit. Check your contract and inclusions list before the walkthrough so you know what should be there.
What a Visual Inspection Can and Cannot Confirm
|
Item |
Observed on site |
Needs records or certificates |
May need specialist testing |
|
Paint, plaster, joinery and floor finish |
Yes |
No |
Rarely |
|
Shower drainage and visible sealant |
Yes |
No |
No |
|
Wet-area waterproofing membrane |
Signs of failure only |
Waterproofing records and photos |
Yes, if leaks are suspected |
|
Roof flashings and gutters |
Where safely visible |
Roof plumbing compliance certificate |
Sometimes |
|
Concealed plumbing and drains |
Visible leaks only |
Plumbing compliance certificates |
Yes, by a licensed plumber |
|
Wiring and switchboard |
Operation of accessible fittings |
Certificate of electrical safety |
Yes, by a licensed electrician |
|
Termite management system |
Visible components and labels |
Installer’s certificate |
Sometimes |
|
Footings and slab |
Visible cracking and movement signs |
Soil report and engineering design |
Yes, by an engineer |
|
Floor levels on flood-affected land |
No |
Survey and approved plans |
Yes, by a surveyor |
Which Building Codes and Australian Standards Apply at Handover?
Homeowners often expect a list of standard numbers. A list is less useful than knowing what each rule means for something you can see or check at handover, and which edition applies to your home.
Start with three distinctions:
- A legal requirement is set by legislation, the National Construction Code (NCC) as adopted in Victoria, or a standard the NCC calls up. Building work must meet it.
- An approved design is what your building surveyor approved: the stamped plans, engineering and specifications. Work should match it.
- A workmanship tolerance describes how much variation in finished work is generally acceptable. Victoria’s main reference is the Guide to Standards and Tolerances.
Your contract can also set a higher standard than any of these. Where it does, the contract matters.
Regulation or standard | What it means at handover |
Building Act 1993 (Vic) | The framework for building permits, surveyors, occupancy permits and practitioner obligations |
Building Regulations 2018 (Vic) | Victorian requirements for permits, mandatory inspections and occupancy, plus land designations such as bushfire prone areas |
NCC 2022 or NCC 2025, as applicable | The minimum performance and construction requirements your home was designed and approved under |
NCC Volume Two, Part H2 | Damp and weatherproofing: how the building keeps water out, including roof drainage and the external envelope |
NCC Volume Two, Part H4 | Health and amenity: wet areas, ventilation and condensation management |
NCC Volume Two, Part H5 | Safe movement and access: stairs, balustrades, barriers and handrails |
AS 3740 | Waterproofing of domestic wet areas, used as one compliance pathway for wet areas |
AS/NZS 3500.3 | Stormwater drainage, including gutters, downpipes and connection to the drainage system |
AS 3959 | Construction in bushfire prone areas, according to the site’s Bushfire Attack Level |
Guide to Standards and Tolerances | Recognised workmanship benchmarks, using the edition that applies to your contract |
How these rules show up at handover
- Wet areas. Under the NCC’s Deemed-to-Satisfy pathway for houses, clause H4D3 points to the ABCB Housing Provisions. Those provisions allow wet-area materials and installation to follow AS 3740 together with Housing Provisions requirements, or to follow the Housing Provisions clauses directly. At handover you can observe the results: floor falls, shower containment and sealant. The membrane itself is verified through records, not by eye.
- Gutters, downpipes and stormwater. Roof drainage and stormwater are plumbing work in Victoria. The Plumbing Code of Australia, given effect by the Plumbing Regulations 2018, references AS/NZS 3500.3. The BPC notes that work commenced on or after 20 October 2025 must comply with the 2025 edition. At handover you can see gutter falls, downpipe connections and ponding. The roof plumber’s compliance certificate covers the rest.
- Stairs and balustrades. Part H5 deals with stair geometry, barrier heights and openings. An inspector can measure accessible balustrades and stairs and flag details that look inconsistent with the requirements for further review.
- Workmanship. Plaster finish, wall straightness, tiling, and concrete cracking are typically measured against the Guide to Standards and Tolerances, which should be read alongside your contract.
A few rules apply to how any of this is reported. An inspector should not state that an observed defect breaches a specific NCC clause without sufficient evidence to support the claim. A visual handover inspection does not certify compliance with every standard in the table. AS 4349.1, the standard for pre-purchase inspections of existing homes, is not the benchmark for assessing new construction.
How Victoria’s 2026 Standards Changes Affect Handover Inspections
Two changes took effect in Victoria in 2026, and both depend on dates.
NCC 2025 from 1 May 2026.
Victoria adopted NCC 2025 on 1 May 2026. The Building and Plumbing Commission (BPC) explains that the new requirements apply to projects in which design work began after that date. Projects that had already begun design or construction can generally continue under the edition that applied when their work started. Many homes handed over in late 2026 were designed and approved under NCC 2022. The applicable edition is identified through your project’s approvals and the transitional arrangements, not by the handover date. Your building surveyor can confirm it.
Guide to Standards and Tolerances 2026 from 1 August 2026.
The BPC’s updated guide applies prospectively from 1 August 2026. It does not apply to contracts entered into, or building work commenced, before that date. For those projects, the previous edition applies. The guide is not legislation and cannot override the NCC, Australian Standards, legislation or your building contract. Where those set a specific requirement, they take precedence.
The practical point is to ask your inspector which edition they have assessed against. A tolerance finding is only as useful as the benchmark behind it.
Practical Completion Inspections in Geelong: What Deserves Extra Attention?
Most of a practical completion inspection is the same wherever the house is built. What changes in Greater Geelong is the site: the drainage approvals, soils, coastal exposure, bushfire requirements and flood overlays that shaped the design. Each one affects which documents matter and which details deserve a closer look.
1. Stormwater drainage and site grading
The City of Greater Geelong requires property owners to connect their stormwater system to the approved legal point of discharge (LPoD) and maintain it in good working order. Owners are responsible for their private system, including gutters, downpipes, pits and underground drains, up to and including that point. Council does not hold records of private drainage layouts.
At handover, look for ponding against the slab, downpipes that are not connected, open or uncovered pits and ground that falls towards the house. Whether the underground connection actually reaches the LPoD cannot be confirmed by looking at the surface. Ask the builder for the drainage plan and the plumber’s compliance certificate, and refer suspected problems to a licensed plumber.
2. Coastal exposure and material suitability
Homes near the coast in places such as Ocean Grove, Barwon Heads, Portarlington and Torquay may be specified with fixings, flashings, roofing, balustrade hardware and finishes suited to a more corrosive environment. Not every coastal property has the same exposure classification. It depends on distance from the water, wind and shelter.
A useful check at handover is whether the installed materials match the specifications. A standard product substituted for a coastal-rated one can look identical on day one.
3. Soil conditions, movement and drainage
Many new estates across Geelong’s growth areas, including Armstrong Creek, Mount Duneed and Lara, are built on reactive clay. The site classification and footing design are set out in the geotechnical (soil) report and the engineer’s documentation. Keep both.
At handover, record any cracking in the slab edge, brickwork or plaster, and note doors that bind. These observations need professional assessment. A crack in a new home is not automatic proof of slab failure, and many are minor shrinkage or finishing issues. Site drainage matters here too, because water collecting against a slab on reactive clay can increase ground movement.
4. Bushfire-prone land and BAL requirements
Parts of Greater Geelong are in a designated Bushfire Prone Area, the Bushfire Management Overlay or both. New homes in a Bushfire Prone Area must be built to AS 3959, and the Bushfire Attack Level (BAL) assessed at the building permit stage sets the construction requirements. The levels run from BAL-LOW through to BAL-FZ (Flame Zone).
At handover, compare the finished work with the approved BAL assessment and building documents. Openings, glazing, screens, external doors, vents, weep-hole protection, and external materials are the areas to focus on.
5. Flood overlays and finished floor levels
Some Greater Geelong land is affected by the Special Building Overlay (SBO), which covers areas subject to localised stormwater flooding. Council says permitted works in the SBO are usually subject to conditions setting minimum floor levels, based on flood advice for the property.
Where your land is affected, the approved flood advice and finished floor levels should match the approved documentation. An ordinary visual practical completion inspection does not independently verify surveyed floor levels. A licensed land surveyor’s certification is the evidence that does.
Five Documents Worth Checking for a Geelong New Home
Which of these apply depends on your site.
- Approved drainage information: the stormwater drainage plan, legal point of discharge details and the plumber's compliance certificate.
- Site or soil report: the geotechnical report showing the site classification the footings were designed for.
- BAL assessment: where the land is bushfire prone, the assessed BAL and the construction requirements it triggered.
- Engineering documentation: slab and footing design, and any engineer's inspection certificates.
- Occupancy permit: issued by the relevant building surveyor, with any conditions noted.
Ripple's building inspections in Geelong cover new estates, coastal towns and established suburbs across the region.
Your Practical Completion Checklist Before Accepting Handover
Use this practical completion checklist on your own walkthrough, or alongside your inspector’s report. It is organised by area so you can work through the home systematically. Take photos as you go and note the room for every item.
It avoids anything unsafe for an unqualified homeowner. Do not climb onto the roof, open the switchboard, remove covers or test gas or electrical systems. Leave those to licensed trades.
1. Building finishes and fixtures
Area | Practical homeowner check |
Walls and ceilings | Look along each wall in raking light for cracks, poor joints, nail pops and patchy paint |
Cornices and skirting | Check for gaps, open joints and missing sections |
Floors | Record damaged boards, lifting edges, scratches, chips and concerning gaps |
Cabinetry and benchtops | Open every door and drawer. Check alignment, soft-close function, chips and that finishes match your selections |
Fixtures | Confirm every fitting in your inclusions list is installed and undamaged |
2. Doors, windows and external envelope
Area | Practical homeowner check |
Windows | Open, close and lock each window. Inspect accessible seals, flyscreens and hardware. Look for scratched glass |
Internal doors | Check each door closes and latches without binding, with even gaps |
External doors | Check locks, seals and thresholds. Look for daylight around closed doors |
External walls | Look for cracking, gaps at junctions and blocked weep holes |
Gutters (from the ground) | Look for gutters that sag, overflow marks and downpipes that stop short |
3. Bathrooms, plumbing and drainage
Area | Practical homeowner check |
Shower | Run it for several minutes. Look for water escaping the intended shower area or pooling on the base |
Wet-area floors | Pour a little water near the waste and check it flows towards the drain |
Sealant | Check silicone is continuous in internal corners and around baths, basins and screens |
Taps and toilets | Run every tap hot and cold. Flush every toilet. Look for drips under sinks and vanities |
Exterior drainage | Look for pooling water and visibly disconnected downpipes or open pits |
4. Safety systems and operational checks
Area | Practical homeowner check |
Smoke alarms | Press the test button on each alarm and note its location |
Lights and power points | Switch every light. Use a phone charger to confirm accessible power points work |
Exhaust fans | Turn on each fan and check it runs and draws air |
Garage | Check door operation and available safety features such as auto-reverse |
Stairs and balustrades | Look for loose handrails, wobbly balustrades and gaps a child could fit through. Report any concern rather than testing it by force |
5. Documentation and agreed work completion
Area | Practical homeowner check |
Occupancy permit | Confirm it has been issued for the address and note any conditions |
Certificates | Ask for plumbing, electrical, waterproofing, glazing and termite management records |
Variations | Check every signed variation has been carried out |
External works | Confirm contracted driveways, paths, fencing and landscaping are complete |
Outstanding items | Get a written list of anything unfinished, with agreed completion dates |
What Happens if Your Inspector Finds Defects?
Almost every practical completion report lists defects. A long report usually means a thorough inspector, not a badly built house. What matters is the type of finding and what you do next.
A useful report separates findings by type. The categories below are a practical reporting framework, not statutory defect classifications.
|
Finding type |
Example |
What the homeowner should do |
|
Safety concern |
A balustrade that moves, an unsecured stair |
Ask for prompt assessment and rectification before occupation |
|
Suspected non-compliance |
A visible detail that looks inconsistent with an applicable requirement |
Ask the builder for clarification and evidence of compliance |
|
Contractual defect |
Work that differs from an agreed specification |
Compare it with the signed contract and approved variations |
|
Incomplete work |
A contracted fixture or finish not installed |
Get written confirmation of when and how it will be completed |
|
Cosmetic workmanship issue |
A visible finish variation |
Check it against the relevant tolerance and the contract’s finish requirements |
How to Record and Communicate Defects to Your Builder
Raise concerns directly with your builder first, in writing, and give them a reasonable opportunity to respond. Consumer Affairs Victoria suggests listing anything faulty or incomplete, speaking to the builder promptly and then sending a written request, together with any agreements about the work, by registered post.
A simple defect log keeps everyone working from the same list. Here is an illustrative example:
|
Field |
Example entry |
|
Defect number and location |
D-07, ensuite shower, northern corner |
|
Observed condition |
Water flows past the end of the screen and pools on the ensuite floor after two minutes |
|
Supporting photograph |
Photo 07a (water on floor), Photo 07b (screen junction) |
|
Contract or technical reference |
Wet-area requirements. Specification item 4.3, frameless screen. Reference to be confirmed with builder |
|
Requested rectification |
Adjust the screen or seal so water stays within the shower area. Check the floor fall to the waste |
|
Builder response and agreed follow-up |
Builder to attend 14 November. Plumber and glazier booked |
|
Reinspection status |
Pending. Retest the shower after rectification |
If the issue is not resolved, the BPC offers a free domestic building dispute resolution service, formerly known as Domestic Building Dispute Resolution Victoria (DBDRV). You must try to resolve the dispute with the builder first. A dispute resolution officer then helps both parties try to reach agreement. If conciliation fails, the BPC can make binding orders or issue a certificate allowing the matter to proceed to VCAT.
Should You Make the Final Payment if Defects Remain?
This is the decision most homeowners worry about, and the answer depends on what remains outstanding and what your contract says.
Consumer Affairs Victoria states that, for a new home, you make the final payment when the work is finished in accordance with the plans and specifications and the occupancy permit has been issued. Until both have happened, the builder is not entitled to the final payment.
That does not mean any defect allows you to hold back the money. Three situations look different:
- Incomplete contractual work. If something in the plans and specifications has not been done, the work is not complete under that test. Get the outstanding items and completion dates in writing.
- Minor finishing concerns. Small items, such as touch-ups or adjustments to a cupboard door, are normally handled via a written defect list and an agreed rectification date. Treating these as grounds to withhold the full final payment can escalate a manageable situation into a dispute.
- A dispute over whether completion has been reached. If you and your builder disagree about whether the home is complete, stop and get advice before deciding what to pay.
Consumer Affairs Victoria advises seeking legal advice before withholding a progress payment and notes that progress payments should not be withheld for defects when the stage itself is complete. Withholding money without a proper basis can put you in breach of the contract.
Before making a disputed payment decision:
- Read the completion, notice and final payment clauses in your contract.
- Separate incomplete work from defects in your inspector’s report.
- Put your position and the outstanding items to the builder in writing.
- Get independent legal advice and, where needed, building advice. The Law Institute of Victoria has a referral service for building lawyers.
- Contact Consumer Affairs Victoria’s Building Information Line (1300 55 75 59) or the BPC if you need guidance.
What Documents Should You Receive at New Home Handover?
Some documents are required for completion. Others are useful records that depend on your project. Keep everything together, digitally and on paper.
| Document or record | Why it matters |
|---|---|
| Occupancy permit | Required before you can occupy a new home and part of the completion test for final payment |
| Approved plans, specifications and signed variations | The benchmark for checking whether the work is complete |
| Plumbing compliance certificates | Cover the plumbing, drainage and roof plumbing work carried out by licensed or registered plumbers |
| Certificate of electrical safety | Issued by the licensed electrician for the electrical installation |
| Other certificates required for your project | For example glazing, waterproofing or termite management records, where applicable |
| Domestic Building Insurance certificate or Home Warranty notice of cover | Shows which scheme applies if something goes wrong later |
| Manufacturer warranties and appliance manuals | Needed for warranty claims and maintenance |
| Insulation or energy rating documentation, where provided | Confirms what was installed against the approved energy design |
| Keys, remotes and access codes | Practical, but often missed in the rush of handover day |
| Written list of unresolved defects and incomplete work | Records what was outstanding at handover and what the builder agreed to fix |
The last item is the one homeowners most often skip. A dated, written list signed or acknowledged by the builder settles the most common later argument: whether a problem existed at handover or appeared afterwards.
What Happens After Handover? Defects, Warranties and Rectification
Handover does not end your protection. Every domestic building contract in Victoria includes warranties under the Domestic Building Contracts Act 1995, including that work will be carried out in a proper and workmanlike manner and in accordance with the plans, specifications and the law. Which insurance scheme sits behind that depends on when you signed your contract.
Domestic Building Insurance vs Home Warranty
Victoria is moving from Domestic Building Insurance (DBI) to Home Warranty for new eligible domestic building work.
| Coverage | Domestic Building Insurance (DBI) | Home Warranty |
|---|---|---|
| Applicable projects | Generally eligible contracts signed before 1 July 2026, with a DBI certificate of insurance. Required for work over $16,000 | Eligible contracts signed on or after 1 July 2026, for eligible work valued over $20,000 |
| When cover may respond | Generally where the builder has died, disappeared or become insolvent | May respond where eligible work is incomplete, defective or non-compliant and the builder fails or refuses to complete or fix it |
| Cover | Generally up to $300,000 for homes up to three storeys, under the policy terms | Up to $400,000 in total per home, subject to eligibility, limits and exclusions |
| Duration | Existing policy terms | Generally up to 6 years for major defects and 2 years for other defects or non-compliant work, from completion |
These are scheme summaries, not guaranteed entitlements. Your cover depends on your contract, your policy or notice of cover and the scheme's conditions.
Home Warranty also has claim deadlines. Claims for defective or non-compliant work generally need to be made within 12 months of when you became aware, or reasonably should have become aware, of the problem. DBI cover does not transfer to Home Warranty.
The two-year window for non-major defects passes quickly. A builder's warranty inspection before it closes records any defects while they may still be covered.
What if the Builder Does Not Rectify the Work?
Document the problem with dated photos and notes, then send the builder a written request to fix it. Keep copies of all correspondence. The BPC expects you to have raised the issue with the builder and given them a chance to respond before it becomes involved.
If that does not work, you can apply to the BPC's dispute resolution service. Under Victoria's 2026 reforms, the BPC can also issue Rectification Orders requiring incomplete, defective or non-compliant work to be fixed or completed. Orders can be issued up to 10 years after the occupancy permit. They are discretionary. The BPC assesses each matter, will not consider an order in every case and prioritises serious issues such as work that makes a home uninhabitable or puts people at risk. Where a Home Warranty claim is made, the BPC must consider a Rectification Order before deciding the claim.
Defects can appear months after handover, once the house has been through a wet winter or a hot summer. Our guide to when construction errors usually show up explains what to watch for.
Why Book an Independent Practical Completion Inspection?
The builder’s walkthrough is run by the people who built the house. The building surveyor’s final inspection concerns occupation, not finish or your contract. An independent practical completion inspection is the one review carried out for you.
Ripple Building Inspections examines the accessible parts of the finished home, covering structural elements, mechanical systems, workmanship, fixtures and finishes. Inspectors compare what they see with your contract documents and record any defects and incomplete work in a report that includes photographs and locations. You can take that report into your walkthrough and use it to agree what will be fixed before you accept the home.
An inspection cannot guarantee a defect-free home or certify the condition of concealed components, such as waterproofing membranes and wiring. Its value is a clear, independent record at the point where your builder can still act on it most easily.
Ripple inspects new homes across Greater Geelong, the Bellarine Peninsula, the Surf Coast and Melbourne’s metropolitan suburbs.